06-10-26 BOF Regular Meeting Agenda & Backup Documents

agenda center agenda

Board/CommissionBoard of Finance
Meeting DateJune 10, 2026
Pages16
File Size0.5 MB
OCR Status Searchable (OCR processed)
Source URLOriginal
Download PDF

Document Preview

Full Text (OCR Extracted)
3.









DATE 
APPROVED
DEPARTMENT
SOURCE
LINE 
ITEM
DESCRIPTION
 APPROVED 
BUDGET 
AMOUNT 
APPROPRIATED/ 
AVAILABLE
AMOUNT 
DESIGNATED
AMOUNT 
ENCUMBERED
AMOUNT 
EXPENDED
COMMENTS
 DATE 
UPDATED 
2/6/2023 BOE
CNR
20560-
55020
CLARK LANE MIDDLE SCHOOL CHILLER 
REPLACMENT
                951,340 
16,419 
-   
96,787                 838,134 Project is wrapping up. Awaiting final invoices to close 
project.
4/24/2026
7/1/2019 BOE
CNR
20560-
57828
QH 1-YEAR RETRO COMMISSIONING
30,000 
-                   30,000 
        -                              -   Initial estimate was considerably higher.  Legislation gave a 
slight reprieve for the inspections, Quaker hill is the oldest 
elementary and will be the first one evaluated. 
4/24/2026
7/1/2020 BOE
CNR
20560-
57842
SCHOOL SECURITY
             2,082,900 
43,220 
23,899              2,015,781 Working on getting a couple of cameras at the High 
School softball field completed and one camera out near 
the street at Quaker Hill school.   These were expected 
as part of phase 2 and will be treated as two separate 
small add on projects to the existing completed system.
4/16/2026
10/7/2024 BOE
CNR
20560-
57893
GREAT NECK FIELD REMEDIATION
                278,750 
19,168 
30,640                 300,192 Project ongoing.  Weekly meetings to be held through 
project.
4/24/2026
7/1/2023 EMERGENCY 
MGMT
CIP
32224-
55908
APCO INTELLICOM GUIDECARD SYSTEM
40,000 
20,000 
-   
    20,000 The APCO Initellicom Guide Card System is actively being 
built.  The APCO Intellicom project is currently being 
worked on by NEXGEN and APCO.  The bridge is completed 
and being testing.
4/8/2026
7/1/2023 EMERGENCY 
MGMT
CIP
32224-
55909
EVENTIDE NEXLOGDX RECORDER
88,701 
88,701 
Recorder bid being readied for distribution.
4/8/2026
9/22/2025 EMERGENCY 
MGMT
CNR
20522-
57022
CONVERSION TO STATE RADIO SYSTEM
             4,600,000              4,600,000 
-                4,647,482 
(47,482) Project ongoing.  Weekly meetings to be held through 
project.
4/8/2026
7/1/2016 EMERGENCY 
MGMT
CNR
20522-
57794
MOBILE & PORTABLE RADIO REPLACEMENT 
PROGRAM
             1,257,577 
21,511 
0 
0 
1,236,067 Awaiting quote for final purchase/programming of radios.
4/8/2026
7/1/2019 FACILITIES
CIP
31120-
55851
ADA IMPROVEMENTS PD/YSB
87,000 
48,636 
0 
12,600 
25,764 Original bid produced costs above approved budget.  
Additional funds to be requested in FY27 budget.
4/22/2026
7/1/2020 FACILITIES
CIP
31121-
55851
ADA IMPROVEMENTS PD/YSB
80,700 
76,061 
0 
0 
4,639 Original bid produced costs above approved budget.  
Additional funds to be requested in FY27 budget.
4/22/2026
7/1/2022 FACILITIES
CIP
31123-
55904
UST REPLACEMENT (EUGENE O'NEILL, 2 tanks)
                260,000 
109,647 
0 
40,028 
110,325 Project complete and remains open for retainage and 
further required testing.
4/22/2026
7/1/2016 FACILITIES
CIP
31117-
55803
PARKING LOT - YSB & POLICE
                300,000 
215,000 
0 
17,800 
67,200 Contract awarded by BOS 4/21/2026.
4/22/2026
7/1/2017 FACILITIES
CIP
31118-
55803
PARKING LOT - YSB & POLICE
                195,320 
138,320 
0 
0 
57,000 Contract awarded by BOS 4/21/2026.
4/22/2026
New Project added - approved since last report or out of regular budget cycle
Project complete but being kept open for retainage (per contract) or final state review and closure
TOWN OF WATERFORD
GENERAL FUND
CAPITAL PROJECT STATUS REPORT 
FY2026 SECOND QUARTER REPORT (January 1, 2026 thru March 31, 2026)
COLOR CODING 
Project is closed/completed and will be removed from next report.
1
4.

DATE 
APPROVED
DEPARTMENT
SOURCE
LINE 
ITEM
DESCRIPTION
 APPROVED 
BUDGET 
AMOUNT 
APPROPRIATED/ 
AVAILABLE
AMOUNT 
DESIGNATED
AMOUNT 
ENCUMBERED
AMOUNT 
EXPENDED
COMMENTS
 DATE 
UPDATED 
New Project added - approved since last report or out of regular budget cycle
Project complete but being kept open for retainage (per contract) or final state review and closure
TOWN OF WATERFORD
GENERAL FUND
CAPITAL PROJECT STATUS REPORT 
FY2026 SECOND QUARTER REPORT (January 1, 2026 thru March 31, 2026)
COLOR CODING 
Project is closed/completed and will be removed from next report.
7/1/2024 FACILITIES
CNR
20511-
57740
COHANZIE REMEDIATION/DEMOLITION
40,000 
40,000 
Project on hold pending final decision regarding property 
(i.e. sell, develop, etc.).
4/26/2026
7/1/2024 FACILITIES
CNR
20501-
57889
PUBLIC SAFETY COMPLEX HVAC
100,000 
100,000 
 Will be a multi-year funding request before project can be 
bid and scheduled.
12/16/2025
7/1/2023 FACILITIES
CIP
31124-
55912
TOWN DOCK REPLACEMENT
                  40,000                   40,000                          -                              -                              -   Port Authority grant received.  Work to begin Summer 
2026.
4/22/2026
2/7/2021 FACILITIES
CNR
20511-
57872
ROOF & HVAC REPLACMENT OF PUBLIC SAFETY 
BULDING
                409,400 
4,769 
0 
3,000 
401,631 Roof portion of project completed.  HVAC portion will be 
completed under approved account 20511-57889
4/22/2026
7/1/2016 FIRE
CNR
20523-
57792
OSWEGATCHIE FIRE BUILDING 
IMPROVEMENTS/REPAIRS
                260,000                 141,111                          -                        8,712                 110,177 Will remain open for repairs to old building while new 
station is being constructed.
4/16/2026
10/6/2025 FIRE
BUILDING 
PROJECT
43323-
57508
NEW OSWEGATCHIE FIRE STATION BUILDING 
PROJECT
           13,319,471              4,148,245 
             8,392,113                 779,113 On-going
4/16/2026
7/1/2019 FIRE
CNR
20523-
57836
FIRE SERVICES OFFICE CARPET REPLACEMENT
                  30,000 
                30,000 
Project will closed.  New Director has other priorities for 
department needs.
4/16/2026
1/24/2025 FIRE
CNR
20523-
57888
GOSHEN ROOF REPLACEMENT
                  60,000 
                60,000 
Bids came in over budget. Leaks have been repaired.  
Project being reviewed on how to move forward to replace 
entire roof.
4/16/2026
7/1/2025 FIRE
CIP
32326-
55923
COHANZIE AIR CONDITIONING
                  15,000                            -                            -                              -                     15,000 Units purchased and awaiting installation.
4/16/2026
7/1/2023 FIRE
CNR
20523-
57777
SCBA UPGRADES
                414,000                      4,135                          -                     47,303                 454,264 Awaiting one additional unit and masks.  Once received, 
project will be complete.
4/16/2026
7/1/2019 FIRE
CNR
20523-
57791
JORDAN TRAFFIC LIGHT UPGRADE
                  35,460                            -                            -                     35,460                            -   Project will be closed.  New Director reviewing more cost 
effective options and will bring new request forward at a 
later date.
4/16/2026
2/6/2023 IT
CIP
34723-
55021
AUDITORIUM MEETING ROOM
                272,000                   62,435                          -                              -                   209,565 Project complete except for integration with webx and 
zoom capabilities.  Testing new wireless video integration 
for presentation boards.
4/16/2026
7/1/2025 IT
CNR
20547-
57775
VIRTUAL SERVERS
                  88,500 
                88,500 
Project is a 2 year project.  2nd year funding requested in 
FY27 capital budget.
4/16/2026
7/1/2023 IT
CNR
20547-
57882
COMPUTER REPLACEMENTS
                  74,925                   46,757                          -                              -                     62,096 On schedule for FYF26 replacement plan.
4/16/2026
7/1/2019 PLANNING
CNR
20511-
57840
POCD
                100,000 
10,104 
0 
0 
89,896 Edits to final draft being completed and full draft to be 
distributed to Commission for review in April.
4/14/2026
7/1/2022 PLANNING
CNR
20511-
57870
MAGO POINT IMPROVEMENTS
                400,000 
20,408 
0 
66,330 
313,262 Final CHRO review of paperwork and contractor has 
mobilized at site to begin work by the end of April.
4/14/2026
2

DATE 
APPROVED
DEPARTMENT
SOURCE
LINE 
ITEM
DESCRIPTION
 APPROVED 
BUDGET 
AMOUNT 
APPROPRIATED/ 
AVAILABLE
AMOUNT 
DESIGNATED
AMOUNT 
ENCUMBERED
AMOUNT 
EXPENDED
COMMENTS
 DATE 
UPDATED 
New Project added - approved since last report or out of regular budget cycle
Project complete but being kept open for retainage (per contract) or final state review and closure
TOWN OF WATERFORD
GENERAL FUND
CAPITAL PROJECT STATUS REPORT 
FY2026 SECOND QUARTER REPORT (January 1, 2026 thru March 31, 2026)
COLOR CODING 
Project is closed/completed and will be removed from next report.
7/1/2024 PUBLIC WORKS
CIP
33025-
55920
NIANTIC RIVER ROAD SIDEWALK REPLACEMENT 
PLAN
25,000 
10,000 
0 
15,000 Grant awarded.  Working on final plan design.
4/22/2026
8/7/2023 PUBLIC WORKS
CNR
20530-
57886
PAVING (OLD NORWICH ROAD)
             1,053,000 
428,823 
0 
59,800 
564,377 WUC completed plastic replacements, Paving and stripping 
completed.  Manhole covers being worked on.  Expected 
completion of July 2026.
4/22/2026
7/1/2025 PUBLIC WORKS
CIP
33026-
55925
ROAD RISK ASSESSMENT
55,000 
9,200 
0 
45,800 
0 On-call engineers to generate quotes for a Sustainability / 
Flooding plan (Niantic River Road).  Contract awarded and 
April meeting scheduled to review with town's 
Environmental Engineer.
4/22/2026
7/1/2021 PUBLIC WORKS / 
LIBRARY
CNR
20536-
57848
LIBRARY HVAC UPGRADE
             1,596,278 
(165,629)
0 
151,306 
1,610,600 Heating completed.  A/C will be testing to be tested when 
warm weather arrives.
4/22/2026
12/1/2025 PUBLIC WORKS
CNR
20511-
57899
LIBRARY ELECTIRCAL PANEL
25,000 
7,000 
18,000 
0 Plan completed.  Eversource expected to complete late 
May 2026.
4/22/2026
12/1/2025 PUBLIC WORKS
CNR
33026-
55022
PAVING  
             1,533,283 
1,475,374 
4,080 
13,125 Project will be scheduled once BOS has awarded contracts 
on 5/5/2026.
4/22/2026
7/1/2025 POLICE
CNR
20529-
57871
POLICE DEPARTMENT BLDG HVAC
25,000 
25,000 
New FY26 project.
4/16/2026
7/1/2022 REC&PARK
CIP
33723-
55838
CHILDREN'S PLAYGROUND EQUIPMENT
40,000 
0
0
40,000
0 Materials ordered.  To be installed late spring 2026.
4/21/2026
7/1/2025 REC&PARK
CNR
20537-
57798
CHILDREN'S PLAYGROUND EQUIPMENT (CIVIC 
TRIANGLE)
25,000 
0
0
25,000
Materials ordered.  To be installed late spring 2026.
4/21/2026
7/1/2024 REC&PARK
CIP
33725-
55921
STENGER PARK BATHROOM & WALKWAY
10,500 
3,300
0
7,200 Plan received and awaiting final invoicing.
4/21/2026
7/1/2024 REC&PARK
CNR
20537-
57878
PLEASURE BEACH ACCESS WALK REPAIRS
                145,000 
145,000
6,000 Original bids were above approved amount.  Awaiting 
quotes from vendors with a narrower scope of work.
4/16/2026
7/1/2021 REC&PARK
CIP
33722-
55896
EQUIPMENT STORAGE PLAN
21,000 
4,250
0
8,805
7,945 Exterior of plan is complete.  Working on interior portion of 
plan for new capital project request.
4/21/2026
7/1/2024 REC&PARK
CNR
20537-
57735
LEARY PARK ROAD/PARKING LOT/DRAINAGE
20,000 
20,000 
0 
0 
0 Original quote is $26,000.  Requesting additional quotes 
from on-call engineering firm.
4/21/2026
7/1/2020 WUC
CNR
20531-
57816
OLD NORWICH PUMP STATION REHABS
             1,680,369 
63,904 
0 
325,506 
1,290,958 Final punch list items  being completed.  Once final invoices 
paid, project will be closed.
4/24/2026
7/1/2023 WUC
CIP
33123-
55019
CONTRACT #1 SEWER INTERCEPTOR EASEMENT 
ACCESS
                250,000 
9,312
0
81,016
159,672 Contract awarded to Advanced Resources.  Work expected 
to by June 2026.
4/24/2026
7/1/2022 WUC
CIP
33123-
55895
ROOF & SIDING REPLACEMENT 
50,000 
16,719
0
0
33,281 Ongoing.  Summer work completed.  Work will be resumed 
Summer 2026.
4/24/2026
3

DATE 
APPROVED
DEPARTMENT
SOURCE
LINE 
ITEM
DESCRIPTION
 APPROVED 
BUDGET 
AMOUNT 
APPROPRIATED/ 
AVAILABLE
AMOUNT 
DESIGNATED
AMOUNT 
ENCUMBERED
AMOUNT 
EXPENDED
COMMENTS
 DATE 
UPDATED 
New Project added - approved since last report or out of regular budget cycle
Project complete but being kept open for retainage (per contract) or final state review and closure
TOWN OF WATERFORD
GENERAL FUND
CAPITAL PROJECT STATUS REPORT 
FY2026 SECOND QUARTER REPORT (January 1, 2026 thru March 31, 2026)
COLOR CODING 
Project is closed/completed and will be removed from next report.
7/1/2018 WUC
CNR
20531-
57685
MITIGATION & CONTROL
                388,303                 235,866 
-                              -                   152,437 Contract signed to pilot new Aiprogram to remove 
subjectivity and standardize process.  Study being 
performed to create targeted approach to work.
4/24/2026
7/1/2025 WUC
CNR
20531-
57894
CROSS COUNTRY SEWER MAIN ACCESS
                200,000                 108,131 
39,883 
10,986 Contract signed and will start after Contract #1 Sewer 
Interceptor Easement completed.  Plan under 
development.
4/24/2026
7/1/2025 WUC
CNR
20531-
57895
WATER TANK ASSET MANAGEMENT
46,222 
2,726 
43,496 Project complete and will be removed from next report.
4/24/2026
7/1/2025 WUC
CNR
20531-
57896
BARLETT CORNER WATR BOOSTER
                166,950                 144,245 
22,705 
-   Requested cost estimate from Haley Ward. Bid 
documentation being prepared.
4/24/2026
8/4/2025 WUC
CNR
20531-
57898
ENGINEERING STUDY
                125,000 
14,569 
-   
92,295 
           18,136 Contract awarded to Resilient Land and Water, LLC.  Study 
about 50% completed.
4/24/2026
4/3/2023 WUC
CNR
20531-
57881
WATER PLASTICS SERVICES REPLACEMENT
             1,431,300                 781,472               200,000 
22,864                 626,965 Work is ongoing.  Continuing to work in conjunction with 
DPW paving schedule.  Moving onto Eversource Roads  in 
District 2 and then town roads in District 2.
4/24/2026
4