Project:
Oswegatchie Fire Station
Bid Package:
General Contracting
Bid Date:
2/27/2026
Budget
$10,315,208
Bidder
A. Base Bid #1 : Gen 
Contracting
B. Base Bid #2 : 
IT/Security/ 
Communications
C. Alternate #1: Sanitary 
Sewer
Bid Total                 
A+B+C
Delta to Budget
Allowances
Unit Prices
A. Secondino & Son, Inc.
$7,545,000.00
$205,500.00
$42,000.00
$7,792,500.00
$2,770,208.00
Submitted
Submitted
Mattern Construction, Inc.
$7,765,000.00
$192,850.00
$25,000.00
$7,982,850.00
$2,332,358.00
Submitted
Submitted
Orlando Annulli & Sons, Inc.
$7,745,000.00
$223,000.00
$25,999.00
$7,993,999.00
$2,321,209.00
Submitted
Submitted
WJ Mountfort Co.
$7,787,000.00
$204,965.00
$41,000.00
$8,032,965.00
$2,282,243.00
Submitted
Submitted
Nosal Builders, Inc.
$7,800,000.00
$239,125.00
$27,000.00
$8,066,125.00
$2,249,083.00
Submitted
Submitted
Milestone Construction Services, LLC.
$7,860,600.00
$197,785.84
$28,750.00
$8,087,135.84
$2,228,072.16
Submitted
Submitted
Pelliter Construction Management
$7,880,000.00
$335,000.00
$27,700.00
$8,242,700.00
$2,072,508.00
Submitted
Submitted
Diversity Construction Group, LLC
$8,284,000.00
$275,000.00
$52,000.00
$8,611,000.00
$1,704,208.00
Submitted
Submitted
The Nutmeg Companies, Inc.
$9,013,520.00
$188,715.00
$18,520.00
$9,220,755.00
$1,094,453.00
Submitted
Submitted
BRD Builders, LLC.
$8,973,000.00
$275,500.00
$30,000.00
$9,278,500.00
$1,036,708.00
Submitted
Submitted
Construx Co, LLC.
$9,940,000.00
$293,920.00
$75,287.00
$10,309,207.00
$6,001.00
Submitted
Submitted
Bentley Builders, LLC.
$10,664,413.00
$164,100.00
$17,287.00
$10,845,800.00
-$530,592.00
Submitted
Submitted
COMMENTS:
1. Bid Total includes Base Bid #1, Base Bid #2 and Alternate #1 (Sanitary Sewer).
2. Allowance values are part of Base Bid #1.

 
Town of Waterford 
Purchasing 
Shea Davy, Purchasing Agent 
15 Rope Ferry Rd, Waterford, CT 06385 
 
 
 
EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
RESPONSE DEADLINE: February 27, 2026 at 2:00 pm 
Report Generated:  Friday, February 27, 2026 
 
SELECTED VENDOR TOTALS   
Vendor 
Total 
Total Communications, 
Inc. 
$50,007.52 
A. Secondino & Son, Inc. 
$7,946,843.75 
Mattern Construction Inc 
$8,249,327.50 
Orlando Annulli and Sons, 
Inc. 
$8,293,064.00 
WJ Mountford Co 
$8,316,992.00 
Nosal Builders, Inc. 
$8,344,173.33 
Milestone Construction 
Services, LLC 
$8,365,595.84 
Pelletier Construction 
Management 
$8,403,288.00 
Diversity Construction 
Group LLC 
$8,765,556.90 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 2 
Vendor 
Total 
The Nutmeg Companies, 
Inc. 
$9,497,842.50 
BRD Builders LLC 
$9,589,177.00 
Construx Co LLC 
$10,606,354.50 
Bentley Builders , LLC 
$11,122,893.75 
 
ALLOWANCES (SEE SECTION 012100)  (Table 1 of 3) 
Allowances (See Section 012100) 
A. Secondino & Son, Inc. 
Bentley Builders , LLC 
BRD Builders LLC 
Construx Co LLC 
Diversity Construction 
Group LLC 
Selected 
Line 
Item 
Description Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
1 
Allowance 
#1: 
Excavation 
and Fill 
(part of 
Base Bid 
#1) 
1 
Whole 
$122,300.00 $122,300.00 $245,000.00 $245,000.00 $278,600.00 $278,600.00 $264,967.50 $264,967.50 $122,500.00 $122,500.00 
X 
2 
Allowance 
#2: Utility 
Connection 
Charges 
(part of 
Base Bid 
#1) 
1 
Whole 
$32,000.00 $32,000.00 $32,000.00 $32,000.00 $32,000.00 $32,000.00 $32,000.00 
$32,000.00 $32,000.00 $32,000.00 
Total 
 
$154,300.00  
$277,000.00  
$310,600.00  
$296,967.50  
$154,500.00 
 
ALLOWANCES (SEE SECTION 012100)  (Table 2 of 3) 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 3 
Allowances (See Section 012100) 
Mattern Construction Inc 
Milestone Construction 
Services, LLC 
Nosal Builders, Inc. 
Orlando Annulli and Sons, 
Inc. 
Pelletier Construction 
Management 
Selected 
Line 
Item 
Description Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
1 
Allowance 
#1: 
Excavation 
and Fill 
(part of 
Base Bid 
#1) 
1 
Whole 
$246,400.00 $246,400.00 $246,400.00 $246,400.00 $246,000.00 $246,000.00 $267,000.00 $267,000.00 $128,500.00 $128,500.00 
X 
2 
Allowance 
#2: Utility 
Connection 
Charges 
(part of 
Base Bid 
#1) 
1 
Whole 
$20,000.00 $20,000.00 $32,000.00 $32,000.00 $32,000.00 $32,000.00 $32,000.00 
$32,000.00 $32,000.00 $32,000.00 
Total 
 
$266,400.00  
$278,400.00  
$278,000.00  
$299,000.00  
$160,500.00 
 
ALLOWANCES (SEE SECTION 012100)  (Table 3 of 3) 
Allowances (See Section 012100) 
The Nutmeg Companies, Inc. 
Total Communications, Inc. 
WJ Mountford Co 
Selected 
Line Item 
Description 
Quantity 
Unit of Measure 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
1 
Allowance #1: 
Excavation and 
Fill (part of Base 
Bid #1) 
1 
Whole 
$245,000.00 
$245,000.00 
$0.00 
$0.00 
$252,000.00 
$252,000.00 
X 
2 
Allowance #2: 
Utility 
Connection 
Charges (part of 
Base Bid #1) 
1 
Whole 
$32,000.00 
$32,000.00 
$0.00 
$0.00 
$32,000.00 
$32,000.00 
Total 
 
$277,000.00  
$0.00 
 
$284,000.00 
 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 4 
ALTERNATES   (Table 1 of 3) 
The undersigned proposes to furnish all Labor, Materials, Equipment and Services necessary to construct the items listed in the 
Alternates described in Section 012300 for the stipulated sum of: 
Alternates 
A. Secondino & Son, Inc. 
Bentley Builders , LLC 
BRD Builders LLC 
Construx Co LLC 
Diversity Construction 
Group LLC 
Selected 
Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
3 
ADD 
ALTERNATE 
#1: 
Sanitary 
Sewer Line: 
Add to the 
Base Bid#1 
Total 
1 
Whole 
$42,000.00 $42,000.00 $17,287.00 $17,287.00 $30,000.00 $30,000.00 $75,287.00 $75,287.00 $52,000.00 $52,000.00 
Total 
 
$42,000.00  
$17,287.00  
$30,000.00  
$75,287.00  
$52,000.00 
 
ALTERNATES   (Table 2 of 3) 
The undersigned proposes to furnish all Labor, Materials, Equipment and Services necessary to construct the items listed in the 
Alternates described in Section 012300 for the stipulated sum of: 
Alternates 
Mattern Construction 
Inc 
Milestone Construction 
Services, LLC 
Nosal Builders, Inc. 
Orlando Annulli and 
Sons, Inc. 
Pelletier Construction 
Management 
Selected 
Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
3 
ADD 
ALTERNATE 
#1: 
Sanitary 
Sewer Line: 
Add to the 
Base Bid#1 
Total 
1 
Whole 
$25,000.00 $25,000.00 $28,750.00 $28,750.00 $27,000.00 $27,000.00 $25,999.00 $25,999.00 $27,700.00 $27,700.00 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 5 
Alternates 
Mattern Construction 
Inc 
Milestone Construction 
Services, LLC 
Nosal Builders, Inc. 
Orlando Annulli and 
Sons, Inc. 
Pelletier Construction 
Management 
Selected 
Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Total 
 
$25,000.00  
$28,750.00  
$27,000.00  
$25,999.00  
$27,700.00 
 
ALTERNATES   (Table 3 of 3) 
The undersigned proposes to furnish all Labor, Materials, Equipment and Services necessary to construct the items listed in the 
Alternates described in Section 012300 for the stipulated sum of: 
Alternates 
The Nutmeg Companies, Inc. 
Total Communications, Inc. 
WJ Mountford Co 
Selected 
Line Item 
Description 
Quantity 
Unit of Measure 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
3 
ADD ALTERNATE 
#1: Sanitary 
Sewer Line: Add 
to the Base 
Bid#1 Total 
1 
Whole 
$18,520.00 
$18,520.00 
$0.00 
$0.00 
$41,000.00 
$41,000.00 
Total 
 
$18,520.00 
 
$0.00 
 
$41,000.00 
 
UNIT PRICES   (Table 1 of 7) 
As required by the Base Bid, should deteriorated or damaged materials be required to be removed as determined by the Architect or 
Owner, the cost to remove and replace the referenced material, (or credit for specified material not provided or installed) including all 
labor, material, equipment, and related furnishings is as follows: 
Unit Prices 
A. Secondino & Son, Inc. 
Bentley Builders , LLC 
Selected Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
X 
4 
Soil 
excavation, 
off-site 
transportation, 
and disposal, 
credit and add 
1 
CY 
$14.00 
$14.00 
Ton 
1 
 
 
$37.50 
$37.50 
Ton 
1 
 
 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 6 
Unit Prices 
A. Secondino & Son, Inc. 
Bentley Builders , LLC 
Selected Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
X 
5 
Compacted 
granular fill 
(CGF), 
provision and 
installation, 
credit and add 
1 
CY 
$29.75 
$29.75 
Ton 
1 
 
 
$56.25 
$56.25 
Ton 
1 
 
 
Total 
 
$43.75  
 
 
 
 
$93.75  
 
 
 
 
UNIT PRICES   (Table 2 of 7) 
As required by the Base Bid, should deteriorated or damaged materials be required to be removed as determined by the Architect or 
Owner, the cost to remove and replace the referenced material, (or credit for specified material not provided or installed) including all 
labor, material, equipment, and related furnishings is as follows: 
Unit Prices 
BRD Builders LLC 
Construx Co LLC 
Selected Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
X 
4 
Soil 
excavation, 
off-site 
transportation, 
and disposal, 
credit and add 
1 
CY 
$32.00 
$32.00 
Ton 
1 
 
 
$95.00 
$95.00 
Ton 
1 
 
 
X 
5 
Compacted 
granular fill 
(CGF), 
provision and 
installation, 
credit and add 
1 
CY 
$45.00 
$45.00 
Ton 
1 
0 
0 
$85.00 
$85.00 
Ton 
1 
 
 
Total 
 
$77.00  
 
 
 
 
$180.00  
 
 
 
 
UNIT PRICES   (Table 3 of 7) 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 7 
As required by the Base Bid, should deteriorated or damaged materials be required to be removed as determined by the Architect or 
Owner, the cost to remove and replace the referenced material, (or credit for specified material not provided or installed) including all 
labor, material, equipment, and related furnishings is as follows: 
Unit Prices 
Diversity Construction Group LLC 
Mattern Construction Inc 
Selected Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
X 
4 
Soil 
excavation, 
off-site 
transportation, 
and disposal, 
credit and add 
1 
CY 
$18.20 
$18.20 
Ton 
1 
27.00  
$25.00 
$25.00 
Ton 
1 
 
 
X 
5 
Compacted 
granular fill 
(CGF), 
provision and 
installation, 
credit and add 
1 
CY 
$38.70 
$38.70 
Ton 
1 
58.00  
$52.50 
$52.50 
Ton 
1 
 
 
Total 
 
$56.90  
 
 
 
 
$77.50  
 
 
 
 
UNIT PRICES   (Table 4 of 7) 
As required by the Base Bid, should deteriorated or damaged materials be required to be removed as determined by the Architect or 
Owner, the cost to remove and replace the referenced material, (or credit for specified material not provided or installed) including all 
labor, material, equipment, and related furnishings is as follows: 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 8 
Unit Prices 
Milestone Construction Services, LLC 
Nosal Builders, Inc. 
Selected Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
X 
4 
Soil 
excavation, 
off-site 
transportation, 
and disposal, 
credit and add 
1 
CY 
$25.00 
$25.00 
Ton 
1 
Per CY  
$25.00 
$25.00 
Ton 
1 
37.5 
 
X 
5 
Compacted 
granular fill 
(CGF), 
provision and 
installation, 
credit and add 
1 
CY 
$35.00 
$35.00 
Ton 
1 
Per Ton  
$23.33 
$23.33 
Ton 
1 
35 
 
Total 
 
$60.00  
 
 
 
 
$48.33  
 
 
 
 
UNIT PRICES   (Table 5 of 7) 
As required by the Base Bid, should deteriorated or damaged materials be required to be removed as determined by the Architect or 
Owner, the cost to remove and replace the referenced material, (or credit for specified material not provided or installed) including all 
labor, material, equipment, and related furnishings is as follows: 
Unit Prices 
Orlando Annulli and Sons, Inc. 
Pelletier Construction Management 
Selected Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
X 
4 
Soil 
excavation, 
off-site 
transportation, 
and disposal, 
credit and add 
1 
CY 
$27.00 
$27.00 
Ton 
1 
 
 
$38.00 
$38.00 
Ton 
1 
 
 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 9 
Unit Prices 
Orlando Annulli and Sons, Inc. 
Pelletier Construction Management 
Selected Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
X 
5 
Compacted 
granular fill 
(CGF), 
provision and 
installation, 
credit and add 
1 
CY 
$38.00 
$38.00 
Ton 
1 
 
 
$50.00 
$50.00 
Ton 
1 
 
 
Total 
 
$65.00  
 
 
 
 
$88.00  
 
 
 
 
UNIT PRICES   (Table 6 of 7) 
As required by the Base Bid, should deteriorated or damaged materials be required to be removed as determined by the Architect or 
Owner, the cost to remove and replace the referenced material, (or credit for specified material not provided or installed) including all 
labor, material, equipment, and related furnishings is as follows: 
Unit Prices 
The Nutmeg Companies, Inc. 
Total Communications, Inc. 
Selected Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
Unit Cost 
Total 
Unit of 
Measure 
Quantity Unit Cost 
Total 
X 
4 
Soil 
excavation, 
off-site 
transportation, 
and disposal, 
credit and add 
1 
CY 
$35.00 
$35.00 
Ton 
1 
 
 
$0.00 
$0.00 
Ton 
1 
000 
000 
X 
5 
Compacted 
granular fill 
(CGF), 
provision and 
installation, 
credit and add 
1 
CY 
$52.50 
$52.50 
Ton 
1 
 
 
$0.00 
$0.00 
Ton 
1 
000 
000 
Total 
 
$87.50  
 
 
 
 
$0.00  
 
 
 
 
UNIT PRICES   (Table 7 of 7) 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 10 
As required by the Base Bid, should deteriorated or damaged materials be required to be removed as determined by the Architect or 
Owner, the cost to remove and replace the referenced material, (or credit for specified material not provided or installed) including all 
labor, material, equipment, and related furnishings is as follows: 
Unit Prices 
WJ Mountford Co 
Selected 
Line Item 
Description 
Quantity 
Unit of Measure 
Unit Cost 
Total 
Unit of Measure 
Quantity 
Unit Cost 
Total 
X 
4 
Soil excavation, 
off-site 
transportation, 
and disposal, 
credit and add 
1 
CY 
$27.00 
$27.00 
Ton 
1 
 
 
X 
5 
Compacted 
granular fill 
(CGF), provision 
and installation, 
credit and add 
1 
CY 
$0.00 
$0.00 
Ton 
1 
42 
42 
Total 
 
$27.00 
 
 
 
 
 
BASE BID #1 (GENERAL CONSTRUCTION)  (Table 1 of 3) 
Base Bid #1 (General Construction) 
A. Secondino & Son, Inc. 
Bentley Builders , LLC 
BRD Builders LLC 
Construx Co LLC 
Diversity Construction 
Group LLC 
Selecte
d 
Line 
Ite
m 
Descriptio
n 
Quantit
y 
Unit of 
Measur
e 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
6 
Lump Sum 
(Fixed 
Fee) 
1 
Whole $7,545,000.0
0 
$7,545,000.0
0 
$10,664,413.0
0 
$10,664,413.0
0 
$8,973,000.0
0 
$8,973,000.0
0 
$9,940,000.0
0 
$9,940,000.0
0 
$8,284,000.0
0 
$8,284,000.0
0 
Total 
 
$7,545,000.0
0 
 
$10,664,413.0
0 
 
$8,973,000.0
0 
 
$9,940,000.0
0 
 
$8,284,000.0
0 
 
BASE BID #1 (GENERAL CONSTRUCTION)  (Table 2 of 3) 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 11 
Base Bid #1 (General Construction) 
Mattern Construction Inc 
Milestone Construction 
Services, LLC 
Nosal Builders, Inc. 
Orlando Annulli and Sons, 
Inc. 
Pelletier Construction 
Management 
Selecte
d 
Line 
Ite
m 
Descriptio
n 
Quantit
y 
Unit of 
Measur
e 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
6 
Lump Sum 
(Fixed 
Fee) 
1 
Whole $7,765,000.0
0 
$7,765,000.0
0 
$7,860,600.0
0 
$7,860,600.0
0 
$7,800,000.0
0 
$7,800,000.0
0 
$7,745,000.0
0 
$7,745,000.0
0 
$7,880,000.0
0 
$7,880,000.0
0 
Total 
 
$7,765,000.0
0 
 
$7,860,600.0
0 
 
$7,800,000.0
0 
 
$7,745,000.0
0 
 
$7,880,000.0
0 
 
BASE BID #1 (GENERAL CONSTRUCTION)  (Table 3 of 3) 
Base Bid #1 (General Construction) 
The Nutmeg Companies, Inc. 
Total Communications, Inc. 
WJ Mountford Co 
Selected 
Line Item 
Description 
Quantity 
Unit of Measure 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
6 
Lump Sum 
(Fixed Fee) 
1 
Whole 
$9,013,520.00 
$9,013,520.00 
$0.00 
$0.00 
$7,787,000.00 
$7,787,000.00 
Total 
 
$9,013,520.00  
$0.00 
 
$7,787,000.00 
 
BASE BID #2 TECHNOLOGY   (Table 1 of 3) 
Can bid on any of the each components or all. 
Base Bid #2 Technology 
A. Secondino & Son, 
Inc. 
Bentley Builders , LLC 
BRD Builders LLC 
Construx Co LLC 
Diversity Construction 
Group LLC 
Selecte
d 
Line 
Ite
m 
Description 
Quantit
y 
Unit of 
Measur
e 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
7 
Cameras 
1 
Whole $55,500.0
0 
$55,500.00 $72,600.0
0 
$72,600.00 $90,500.00 $90,500.00 $85,504.00 $85,504.00 $76,000.00 $76,000.00 
X 
8 
Phone 
System/Network/Communicatio
ns 
1 
Whole $84,000.0
0 
$84,000.00 $68,000.0
0 
$68,000.00 $150,000.0
0 
$150,000.0
0 
$154,976.0
0 
$154,976.0
0 
$127,000.0
0 
$127,000.0
0 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 12 
Base Bid #2 Technology 
A. Secondino & Son, 
Inc. 
Bentley Builders , LLC 
BRD Builders LLC 
Construx Co LLC 
Diversity Construction 
Group LLC 
Selecte
d 
Line 
Ite
m 
Description 
Quantit
y 
Unit of 
Measur
e 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
9 
Door card access system/card 
automation 
1 
Whole $66,000.0
0 
$66,000.00 $23,500.0
0 
$23,500.00 $35,000.00 $35,000.00 $53,440.00 $53,440.00 $72,000.00 $72,000.00 
Total 
 
$205,500.0
0 
 
$164,100.0
0 
 
$275,500.0
0 
 
$293,920.0
0 
 
$275,000.0
0 
 
BASE BID #2 TECHNOLOGY   (Table 2 of 3) 
Can bid on any of the each components or all. 
Base Bid #2 Technology 
Mattern Construction 
Inc 
Milestone Construction 
Services, LLC 
Nosal Builders, Inc. 
Orlando Annulli and 
Sons, Inc. 
Pelletier Construction 
Management 
Selecte
d 
Line 
Ite
m 
Description 
Quantit
y 
Unit of 
Measur
e 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
7 
Cameras 
1 
Whole $72,600.0
0 
$72,600.00 $69,723.7
0 
$69,723.70 $64,295.00 $64,295.00 $72,000.00 $72,000.00 $75,000.00 $75,000.00 
X 
8 
Phone 
System/Network/Communicatio
ns 
1 
Whole $85,500.0
0 
$85,500.00 $96,750.0
0 
$96,750.00 $150,000.0
0 
$150,000.0
0 
$122,000.0
0 
$122,000.0
0 
$190,000.0
0 
$190,000.0
0 
X 
9 
Door card access system/card 
automation 
1 
Whole $34,750.0
0 
$34,750.00 $31,312.1
4 
$31,312.14 $24,830.00 $24,830.00 $29,000.00 $29,000.00 $70,000.00 $70,000.00 
Total 
 
$192,850.0
0 
 
$197,785.8
4 
 
$239,125.0
0 
 
$223,000.0
0 
 
$335,000.0
0 
 
BASE BID #2 TECHNOLOGY   (Table 3 of 3) 
Can bid on any of the each components or all. 

EVALUATION TABULATION 
IFB No. IFB# 26-004 
Oswegatchie Fire House -New Construction 
 
 
EVALUATION TABULATION                     
Invitation For Bid - Oswegatchie Fire House -New Construction 
Page 13 
Base Bid #2 Technology 
The Nutmeg Companies, Inc. 
Total Communications, Inc. 
WJ Mountford Co 
Selected 
Line Item 
Description 
Quantity 
Unit of 
Measure 
Unit Cost 
Total 
Unit Cost 
Total 
Unit Cost 
Total 
X 
7 
Cameras 
1 
Whole 
$83,490.00 
$83,490.00 
$0.00 
$0.00 
$66,280.00 
$66,280.00 
X 
8 
Phone 
System/Network/Communications 
1 
Whole 
$78,200.00 
$78,200.00 
$50,007.52 
$50,007.52 
$111,975.00 
$111,975.00 
X 
9 
Door card access system/card 
automation 
1 
Whole 
$27,025.00 
$27,025.00 
$0.00 
$0.00 
$26,710.00 
$26,710.00 
Total 
 
$188,715.00  
$50,007.52  
$204,965.00