Oswegatchie
Fire
Station
21-May-25]
Project Schedule
Planned ion Mar [ Apr Nov | Dec | Jan | Feb Nov E
Name m | Duration Start Finish [TT TOI TUT TT
Milestone Mile 255d | 20-Aug-25 | _ 21-Aug-26 Milestone
GC Notice to Proceed, Mobilization M100 ~0d | 20-Aug-25 {C Notice to Proceed, Mobi
TCO/Substantial Complet M900 od 28-May-26 ©+IC0/Substantial Completion
‘Owner Occupancy M990 18-Jun-26 }@<Dwner Occupancy
Construction Complete - 7 M995 od - 21-Aug-26 © Construction Complete
Project Closed Out M1005 Od 21-Aug-26 yg ject Closed Out
Phase 1 New Fire Station. WBS21 41,1484 | _02-Nov-23@J| 06-Jul-26 Phase 1 New Fire Station
Preconstruction Precon 947d 17-Sep-25. Preconstruction
‘Schematic Design PRE1010 180d (04-Nov-24 EJ | Design
Phase 1 Enviconmental Assessment PRE1000 16d 30-Apr-24
Design Development PRE 1020 120d | 04-Nov-24 GQ | 20-Jan-25 GY fam Design Development
P&Z Application/ Initial Review PRE1030 78d T-Mar-25 Z Appl
‘SD Estimate & Reconciliation PRE1040 206 24-Jan-25 GY
Construction Documents — ~[PRE1090 45d 16-May-25
P&Z Final Review/Approval PRET130 204 29-Apr-25
Conservation Review Process PRE1060 30d 23-Apr-25
CD Estimate and Reconciliation PRE1070 20d | 27-May-25@§| 23-Jun-25
Value Management & Plan Adjustements PRE1100 tod | 24-Jun-25 08-Jul-25 t & Plan Adjustements
RTM Review and Approval PRE1080 2a| _27-dun-25 30-Jun-25 fand Approval
Traffic Permit —_ PRET110 20d | 01-Jul-25 29-Jul-25 raffig Permit
CT DEEP (Stormwater) - PRE1120 30d/ 09-Jul-25, 19-Aug-25, Ff DEEP (Stormwater)
GC RFP Process/Bid Period PRE1150 20d| 09-Jul-25 | 05-Aug-25 iC RFP Process/Bid Period
“Scope Reviews and Recommendation to Award | PRE1160 Sd] 06-Aug-25 12-Aug-25 pe Reviews and Recommendation to Award
RTM Approval to Award PREI170 5d] 13-Aug.25 19-Aug-25 _ | M Approval to Award
Building Permit ~ PRE1140 20d| 20-Aug-25 17-Sep-25 Building Permit
Phase 2 Environmental Soil Characterization PRE1050 tod] 20-Aug-25 | 05-Sep-25 Phase 2 Environmental Soil Characterization,
‘Submittals/Material Procurement. Submit 221d| 20-Aug-25, 06-Jul-26 ‘Submittals /Material Procurement
Submit Major Electrical Submittals PRO1090 40d | 20-Aug-25 16-Oct-25 submit Major Electrical Submitals
Submit Steel & Joist shop drawings PRO1070 35d 20-Aug-25 | 08-Oct-25 _ omit Steel & Joist shop drawings
Submit Aluminum Window Shop Drawings PRO1040 30d| 20-Aug-25 | _01-0ct-25 it Aluminum Window Shop Drawings
|Site Logistics and Start Up Submitta's____—_| PRO1000 tod} 20-Aug-25 | 03-Sep-25 ies and Start Up Submittals
|S Current @ Milestones : = .
Hi Progess FR summary Oswegatchie Fire Station D
WB
Critical
JRevision [checked [Approved
-Mar-35 ipae
27-May-25 odore

Project
Schedule
2026
Planned un |
Name 1D Duration Start Finish I
‘Submit Finishes and Specialty Materials PROTO 60d [20-Aug-25 _|_14:Nov-25 ‘Submit Finishes and Specialty Materials
‘Submit Steel AB Plans PRO1030 tod | 20-Aug-25 | 05-Sep-25 nif Bfeel AB Plans
‘Submit Doors Frames and Hardware Submittals _| PRO1100 26d [20-Aug-25 | 25-Sep-25 Sdtmit Doors Frames and Hardware Submittals
Submit Rebar Shop Drawings - PRO1060 10d] 20-Aug-25 | 03-Sep-25 subrpit Rebar Shop Drawings
Submit Electrical Switchgear PRO1010 35d| 20-Aug-25 | 08-Oct-25 1 cal Switchgear
5 25d | 20-Aug-25 24-Sep-25 Ht
20d] 20-Aug-25 | 17-Sep-25 i
‘Submittals for Pool Equipment | PRO1I20 20d | 20-Aug-25 17-Sep-25 iftals for Pool Equipment
Submit Roof insulation Shop Drawings PRO1020 10d| 20-Aug-25 03-Sep-25 aT f Insulation Shop Drawings
‘Approve Foundation Rebar Shop Drawings PRO1130 Sd| 04-Sep-25 | 10-Sep-25 Foundation Rebar Shop Drawings
Fabricate and Delivery Concrete Rebar tod ifate and,
Steel AB Fab & Deliver tod 1 AB Fab & Deliver
5 15d] 18-Sep-25 rove Sitework Submittals
iF 66d | 25-Sep-25 MEP Coordination
___ Approve Major Mechanical Equipment PRO1180 tod | 25-Sep-25, prove Major Mechanical Equipment
‘Approve Doors, Frames and Hardware Submittals _ | PRO1190 204 26-Sep-25, "peprove Doors, Frames and Hardware Submits
‘Approve Aluminum Window Shop Drawings PRO1200 10d] 02-0c1-25 ‘prove Aluminum Window Shop Drawings
‘Approve Finishes and Spec! 60d | 02-Oct-25 prove Finishes and Specialty lems|
_ ood | 09-0¢t-25 Jajor Equipment Pocufement
rement PRO1220 185d| 09-Oct-25 Electrical $witchgear Procurement
“Finalize Steel Shop Drawings and Calculations PRO1230 10d] _09-0ct-25 nalize Steel Shop Drawings and Calculations.
‘Approve Str PROT240 Sd] 09-Oct-25 prove Structufal Steel & Detk/Joists
‘Approve Major Electrical Submittals PRO1260 tod | 17-0ct-25
Fabricate and Delivery Aluminum Windows PRO1270 60d | 17-0ct-25 | 14-Jan-26 iminlum Windows
—_| PRo280 45d{_24-0ct-25 | _30-Dec-25 abficate & Delivery Struct Steel, Doist/Dec
PRO1290 40d|" 27-0ct-25 | 23-Dec-25 lorigate and Olivery Door Frai
Fabricate and Deliver Doors & Hardware PRO1300 65d| 27-Oct-25 | 29-Jan-26 Fabricafe and Deliver Doors & Hardware
Procure Finishes and Specilaty Materials PRO1310 20d] 31-Dec-25 | 28-Jan-26 ProcurefFinishes and Specilaty Materials
Construction Cons 210d| 20-Aug-25 | 18-Jun-26 ruction
] Site PrepjUtifies
~ Temporary Fence SITEI1000 3d [20-Aug-25 | 22-Aug-25 fempotaty Fenke |
Clearing and Grubbing simeni010 | 3d] 25-Aug-25 | 27-Aug-25 Cel ‘and Grubbing
@ Milestones . . .
Ba Progress PA summary Oswegatchie Fire Station BD
MBB
Critical
[pate [Revision [checked [approved |
fos.nian25 [update
20-May-25 [uodate Waterford Connecticut DOWNES
p-May-25 care TT

Oswegatchie Fire Station ail
Project Schedule
20% 2026
Planned en [Feb | Mar [ Apr | May “jun
Name m Duration Start Finish FTTITILIEE ELLE ut
Erosion Control SITEI1020 2a] 26-Aug-25 | 27-Aug-25
Stripping Topsoil SITENIO30, td] 28-Aug-25 | 28-Aug-25
Sanitary Sewer Systems SITEr1050 20d| 29-Aug-25 | 26-Sep-25
Site rough grading SITEI1040 2d| 29-Aug-25 | 02-Sep-25
‘Storm Water Sewer Systems SITEI1060 15d] 29-Sep-25 | 20-Oct-25 ej Systems
Underground FP/Domestic Water Line SITEIIO70 isd] _21-0ct-25 | 10-Nov-25 Undergrolind F?/Domestic Water Line
Foundation Excavation STRU1000 Sd] 18-Sep-25 | 24-Sep-25
FRP Foundation Footings __| stRu1010 yod| 25-Sep-25 08-Oct-25 [FEB FR youndation Footings
FRP Foundation Walls/Pier Footings STRUIO20 15d] o2-0c-25 | 23-0ct-25 HEP Foundatibn Walls/Pier Footings
Underground Plumbing STRUIO40 tod | 24-0ct-25 | 06-Nov-25
Foundation Backfil/ Protection Board STRUI050 8d] 24-0ct-25 | 04-Nov-25 tion Board
Underground Electrical STRU1050 __ Sd] 31-0ct-25 | 06-Nov-25
Prep for Slab-on-Grade _ STRU1060 2d| 07-Nov-25 10-Nov-25
Place Concrete S06 ‘STRUI070, 2d] 12-Nov-25 | 13-Nov-25
| Building Envelope
Install Exterior CFMF/Sheathing ENVE1000 20d | 14-Nov-25 12-Dec-25 IF/Sheathing
Roofing ENvero1o | 15d] 15-Dec-25 | 06-Jan-26 fing
Install Exterior AVB/Flashings @ © ENVE1020 tod] 15-Dec-25 | _29-Dee-25 AVB/Flashings @ Extetior
Install Veneer Masonry ENVE1030 15d] _30-Dec-25 | 20-Jan-26 tall Veer Masonry
install Exterior finish ENVE1040 tod | 06-Jan-26 | 19-Jan-26 fe finish
Windows & Glass ENVE1050 od] 15-Jan-26 | 28-Jan-26 & Glass
Install Exterior siding ENVE1060 Jod| 21-Jan-26 | _05-Feb-26 xterlor siding
Building Enclosed ___ | ENVE1070 “Od 28-Jan-26
Temporary Environmental Controls ——————*;ENVE1080 isd | 29-Jan-26 18-Feb-26 controls
Roofing Sheetmetal and Copings _ ENVE1090 10d | 04-Feb-26 17-Feb-26 lea
‘Set HVAC Equipment ENVE1700 10d | 05-Mar-26 18-Mar-26
{terior Construction
Re an terior Constfuction
‘Set Door Frames @ CMU Partitions coniooo | —_Sd|_24-Dec-25 | _31-Dec-25
Non-Bearing CMU Partitions __| conto10 __15d| 24-Dec-25 15-Jan-26
Install Plumbing Carriers/Water Supply Lines __| CON1020 isd[ o2-Jan-26 | 22-Jan-26 ipsfall Plumbing Carriers/Water Supply Lines
3 Current @ Milestones A o =
BE rows PA summary Oswegatchie Fire Station DB
GR
Critical
e Revision Jeheckea [approves
Mo Roaate
20-May-25 lvodote Waterford Connecticut DOWNES
7-May-25 lvedate

Oswegatchie
Fire
Station
27-May-25|
4|
Planned Mar [Aug
Name 1D Duration Start Finish ia Tot
Electrical Overhead Raceways/Conduits/Panel... | CON1060_ tod] 09-Jan-26 | 22-Jan-26 [Pam Flectrical oy induits/Panelboard Tubs
Fire Protection Mains/Branches CON1040 15d | 09-Jan-26 | 29-Jan-26 Fire Protegtion Mains /Brarjch
Overhead Ductwork/Boxes CON1050 25d | __ 09-Jan-26 12-Feb-26 Pverhead Ductwork/t
Overhead HVAC Piping/Ceiling Eqmt CON1030 20d | 09-Jan-26 | _05-Feb-26 o wea HVAC Piping, Eqmt
Plumbing Waste & Vent ‘CONTO80 20d] 16-Jan-26 12-Feb-26 Plumbing Waste & Vent
Slab Moisture Mitigation ‘CONT070 tod] 16-Jan-26 29-Jan-26 lab Moistlire Mitigation
Inwall Electrical@LGMF/Branch Wiring CON7100 Sd [23-Jan-26 12-Feb-26 ipwall Electrical@LGMF/Brahch Wiring
Plumbing Insulation CON1090 10d | 23-Jan-26 | _05-Feb-26 Insulation
Install LGMF Partitions/w Door Frames CONTIIO 10d] 30-Jan-26 12-Feb-26 Ay stall [GME Partitions Dor Frames
Masonry Chase Walls ‘CONTI20 10d | 06-Feb-26 19-Feb-26 Masonry Chase Walls
Low Voltage Systems Rough _ | cont140 10d | 43-Feb-26 26-Feb-26 Low Voltage Systems Rough
GWE Walls ‘CONTI30 15d |_13-Feb-26 | 05-Mar-26 GB Walls
HVAC Insulation ‘CONTISO Bd|13-Feb-26 | 24-Feb-26 Insult
Frame LGMF Cellings/Soffits Fascias CON1160 8d] 16-Feb-26 | _25-Feb-26 rae Loe Soyits/Fascias
Install Ceramic Tile Walls @ Toilet Rooms CONT180 tod | 25-Feb-26 | 10-Mar-26 [PPP Ceramic Tie Weis @ Toilet Aooms |
Tape/Sand Walls - CON1170 tod | 25-Feb-26 | 10-Mar-26 pe/Sand Walls |
Sheetrock @ GWB Cellings/Soffits/Fascias CONTI90 3d] 26-Feb-26 | 02-Mar-26 SHlettrock @ GWB Ceilings Soffits Fascias,
Tape/Sand GWB Ceilings/Soffits/Fascias CON1200 4d| 02-Mar-26 05-Mar-26 ane/Sand GWB Ce ine s/Soffits /Fascias
Epoxy Flooring CON1230 10d | 14-Mar-26 24-Mar-26 | Epoxy Flooring!
Install Plumbing Fixtures @ Toilet Rooms CON1210 Tod] 11-Mar-26 | 24-Mar-26 al stall Plumbing Finjures @ Toit Rooms |
ime & 1st Coat Paint ___| €ON1220 tod | 11-Mar-26 | 24-Mar-26 [Pamifrime & txcose Pape
Install Acoustical Celling Grid CON1240 yod| 12-Mar-26 | _25-Mar-26 [stall Acoustic cing Gia
Install Light Fixtures CON1250 tod | 13-Mar-26 | _26-Mar-26 appeal Ligne Fire
HVAC Eqmt Startups CON1260 isd | 19-Mar-26 | 08-Apr-26 HVAC Eqmt Btarlups
Install RGD's CON1270 5d [20-Mar-26 | 26-Mar-26
Protection Heads CON1280 3d| 23-Mar-26 | 25-Mar-26 ctipn Heads
ig Devices/Light Controls CON1350 Jod| 25-Mar-26 | _ 07-Apr-26 Deyices/Light Gontrots
rk /Casework/Finish Carpentry CON1320 15d | 25-Mar-26 15-Apr-26 ifort /Casework/Finish Carpentry
isc Specialties CON1340 Sd] 25-Mar-26 | 31-Mar-26 sc Specifies
Final Coat Paint CON1290 15d | 25-Mar-26 15-Apr-26 Final Coat Pain!
CON7330 Sd] 25-Mar-26 | 31-Mar-26 let Partitjons
CON1300 Sd] 25-Mar-26 | 31-Mar-26 iste Fire Algrm tevices
Ba Progress P= summary Oswegatchie Fire Station Dd
ition [checked [Approved
pate
[20-May-25 update Waterford Connecticut DOWNES

Oswegatchie
Fire
Station
5
Project Schedule
Planned ‘Jun | Jul | Aug [Sep | Oct [Nov | Dec J Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct
Name ID Duration Start T i TILL
Hang Doors/Hardware CON1360 15d | 25-Mar-26 15-Apr-26
install LV System Devices/Finishes (CCTV/Sec... | CON1310 sd] 25-Mar-26 31-Mar-26 stpll LV System Hevices/Finishes (CCTW/Security, etc.)
Final Above Ceiling inspections =| CON1370 23 [27-Mar-26 30-Mar-26 Ing} Above Ceiling Inspection:
Padout Ceiling CON1380 10d | 31-Mar-26 14-Apr-26 adout Ceiling
Install Flooring/Base ‘CON1400_ 25d| 01-Apr-26 (06-May-26 —_
Install Toilet Accessories CON1410 3d] 01-Apr-26 03-Apr-26 ccessories
Fire
Alarm
Ringout
~_|
cOn1390
10d|
01-Apr-26
15-Apr-26
ire
Alarm
Ringout
Testing, Balancing and Inspections CON1420, 10d 16-Apr-26 29-Apr-26 Testing| Balancing and Inspections
Pre-Punch/Broom Clean CON1430 5d | 07-May-26 13-May-26 re-Punch/Broom Clean
Punchlist & Final Cleaning _ CON1450, 10d | 14-May-26 28-May-26 eaning
Final Completion All Trades CON1440 Sd] 14-May-26 20-May-26 Trades
Final Inspections & Substanti ‘CONT460 Sd| 21-May-26 | 28-May-26 Substantial Completion
‘Owner Move-In / Occupancy CON1470 15d | 29-May-26 18-Jun-26 th / Occupancy
Site Concrete __| SITEN1000 21-Jan-26 10-Feb-26
Stormwater Detention Systems SITEN1010 10d | 04-Feb-26 17-Feb-26 yn Systems.
Paving = ‘SITEN1020 10d| _18-Feb-26 03-Mar-26
Site Improvements 30d| 08-Apr-26 20-May-26 ite [mprovements
Site Signage SITEI1040_ Sd] 21-May-26 28-May-26 Site Signage
Phase
2
Demolition
of
Existing
Bldg.
WBS31
60d|
29-May-26
21-Aug-26,
hase
2
Demolition
of
Existing]
Adjust temporary fence DEMO1000 24] 29-May-26 | 01-Jun-26 just Teoma
Exist Bldg Hazmat Removal _ DEMO1010 15d] 02-Jun-26 22-Jun-26 ‘Exist Bldg Hazmat Removal
Demolition of exist bldg. DEMO1020 20d | 23-Jun-26 21-Jul-26 tion of exist bldg.
Back 1g foundations /grade site DEMO1030, od] 22-Jul-26 (04-Aug-26 Il existing foundations /gradt
Site Concrete DEMO1040 5d [05-Aug-26 11-Aug-26 Concrete
Paving DEMO1050 Sd} 12-Aug-26 18-Aug-26
Site Improvements DEMO 1060 3d| 19-Aug-26 | 21-Aug-26 fe Improvements
Closeout Close 40d | 26-Jun-26 21-Aug-26 — Hroseout
Final Completion (O&Ms/Asbuilts, etc...) ‘CLOS1000 40d | 26-Jun-26 21-Aug-26 ‘inal Completion (O&Ms/Asbu}
a
current
@
Miestones
oe
.
Pa Summary Oswegatchie Fire Station D
GB
Critical
ate [Revision [checked [Approved
[20-May-25 luodare Waterford Connecticut DOWNES
27-May-25 [Update -