Oswegatchie Fire Station Building Committee - Minutes - 01/04/2024
agenda center minutes
| Board/Commission | Oswegatchie Fire Station Building Committee |
|---|---|
| Meeting Date | January 04, 2024 |
| File Size | 0.1 MB |
| OCR Status | Searchable (OCR processed) |
| Source URL | Original |
Document Preview
Full Text (OCR Extracted)
[pic]
Oswegatchie Fire Station Building Committee Special Meeting
Minutes
January 4, 2024
Meeting called to order at 5:30pm
Pledge of Allegiance
Members Present: Robert Tuneski, Matthew Blankenship, Jennifer Bracciale,
Rocco Bracciale, Wayne Gilpin, Ted Olynciw, Beth Sabilia, Paul Rafuse,
Richard Muckle
Guests: Brandishea (Shea) Moses, Director Michael Howley, Twig Holland,
Attorney Nick Kepple
• Public Comment: None
• Opening Remarks: After tonight R. Tuneski will have a very accurate
schedule to provide to committee members by the next regular meeting.
• Motion to approve the minutes for December 19, 2023 with the following
correction:
Correct Rich Bracciale to Rich Muckle – R. Muckle
Second – P. Rafuse
For – R. Tuneski, M. Blankenship, J. Bracciale, R. Bracciale, W.
Gilpin, P. Rafuse, R. Muckle
Abstain – B. Sabilia, T. Olynciw
Silver, Petrucelli & Associates (SP&A) delivered their presentation to the
committee at 5:40pm
Responses to questions posed to vendor:
• Response to global supply chain issues and estimates:
Vendor recommended pre-purchasing critical items which is a bit of a
risk to the Town due to purchasing items before there is a final bid.
They will manage those risks to avoid delaying a project. If the
project can be figured out during design and development a plan will
be mapped out and do early bid packages.
T. Holland: Are early bid packages direct from the manufacturer?
Yes – Invite to bid for material only purchase or tie into any federal
or state consortium. Some CROGS are looking at pre-purchase
agreements so you are not bidding it you are procuring it over
consolidated items. Manufacturers are doing that so you have a better
source line. Addressing skilled labor – the state bonded, on the
educational side, 1.1 billion dollars in November. There is concern
is finding general contractors along with the skill set to hire.
• Response to constructor encountering significant challenges and the
ability to offer alternatives:
Procuring a switch gear – problem was handled by adjusting the phases
of a project. Another switch gear issue was handled by installing
temporary buses and disconnects.
• Response to most challenging event:
Community Rec Center in New London – A lot more foundation work was
needed. Site contractor, pile designer and design team met and came
up with different solutions – least expensive, fastest solution, what
is the fastest solution moving forward. A blended effort was decided
upon which caused only a 3 week delay.
• Response to the firm's proposed schedule: T. Holland questioned if it
is possible to accelerate the design portion so site, steel, concrete
& early bid packages could happen by November 2024.
It is possible an early site package could be issued. This could be
looked at as a phase of starting early construction. Vendor will also
be determining what processes can be done at the same time (i.e.,
permitting).
• Response to how they would address any special equipment/needs:
Vendor does not see any particular complications working with this.
Will work with Town on equipment list. Meeting minutes will be
provided to committee to determine if all Town’s concerns are
addressed.
• Phase I Environmental Study is already being contracted out and it
appears on vendor’s bid package:
Vendor had excluded the Environmental piece.
• T. Olynciw asked how SP&A would treat the work product by a previously
hired architectural firm:
Take information, review it and build what they can but will probably
start from the beginning to build a 3-D building information modeling.
• B. Sabilia asked if communication design, wiring, etc. is included:
They work with our vendors to organize security and IT systems. They
make provisions for equipment in the building. This cost would be
rolled into below the line in the soft cost.
• B. Sabilia asked about space needs and who would be at the table to
ask these questions: The Interior Designer and an architect and we
delegate someone who has the best knowledge ie. the Chief and higher
ranking officers.
• B. Sabilia asked if they do public engagement around projects:
Yes – They understand these projects are part of the tax payers and
community. They present to the membership and the public.
• P. Rafuse asked if the vendor aims to incorporate the new NFPA Codes
and Regulations into the building design. More specifically some are
not requirements but are new technologies that the NFPA recommends
that become requirements. Is that something you incorporate ahead of
time or is that something you look to us for:
Vendor stays up to date on NFPA requirements but welcome any input.
Vendor is willing to do that but is cautious about implementing newer
technologies. Will discuss these issues with the committee if the
need arises.
• J. Bracciale asked about the Woodbridge Fire Dept.:
It was all a new building and a portion of it was intended to look
like an old meeting house and mimic the Town Hall across the street.
• J. Bracciale asked if the aesthetics of the Town are taken into
consideration:
Yes. A reference to other projects was given.
• R. Bracciale asked if this project is a good candidate for a pre-
engineered building or conventional construction and have they seen
lead times for pre-engineered building from design to delivery:
Will have to analyze the project before making a statement. Lead time
depends on the manufacturer.
• R. Muckle stated cost and schedule are the 2 primary drivers. What
takes place between now and March when the project would begin:
Survey and site could be in the cue. The team would be assembled.
Programming could be done. Once that is solidified other things can
run parallel, i.e., site work, due diligence, wetland mapping that can
happen early. The bulk of the work would begin mid-March.
• W. Gilpin asked their availability to start on this project:
Starting in mid to late March, yes.
• R. Tuneski asked if SP&A have any design awards:
Yes, East Hartford Fire House and the Willimantic Eastern Fire
Training Academy.
• R. Tuneski asked if they will survey recent history of our building
practices to determine what solutions did or did not work in the
applications they were introduced to:
The team would talk to the person responsible for maintaining the
Town’s facilities.
• R. Tuneski asked if they will do design reviews along the way and will
they be predicated on the extent of work accomplished i.e., 50%, 75%,
100% review. How will design development and the review of
information be handled:
Vendor will pick the percentages that the committee desires. Vendor
can establish at what critical mass points the committee would want to
see each document.
• R. Tuneski – Construction documents – Any reason why construction
documents cannot begin after the 50% or 75% design review or is it
necessary to wait until the design development is 100% complete:
Traditionally wait until it is complete to get the full estimate.
This will give the committee the clarity if the vendor is on budget so
do not want to get too far ahead of the game and possibly have to do
things twice.
• R. Muckle – based on experience what is a reasonable estimate for
beginning construction i.e., shovels in the ground:
This design will take most of 2024. Construction could be done 12
months. Starting point depends on the calendar. Highly recommend not
rushing the project as this could lead to issues with the building
down the road.
The Galante Architecture Studio (TGAS) delivered their presentation to the
committee at 7:04pm
Responses to questions posed to vendor:
• Response to global supply chain issues and estimates:
The firm was very accurate with their estimates among the global
supply chain issues.
• Response to constructor encountering significant challenges and the
ability to offer alternatives:
An example was given that a temporary solution was found when a switch
gear for a generator was delayed.
• Response to most challenging event:
Many issues with renovating a historic building. A redesign
eliminated the need for the customer to build new building at a cost
of $41 million dollars.
• Explain the firm's proposed schedule:
Begin in 4-5 months, design and develop schematics summer 2024,
construction June 2025, finished March 2026.
• Response to how they would address any special equipment/needs:
This is done during the programming phase by determining any
idiosyncrasies and make adjustments accordingly.
• Response to a better detail of fees:
State of Massachusetts does not allow the negotiation of fees prior to
being hired. Vendor stated he would need to go back to office and
look at the analysis.
• T. Olynciw asked for a ballpark square footage cost:
$800-$900 per sq. ft.
• B. Sabilia asked how space needs are determined:
Sit with chief and department representatives. Vendor brings what
they think to the table and listens to what the department needs are.
• P. Rafuse asked if vendor incorporates the newer NFPA recommendations
in the design phase or wait until they become requirements:
Vendor incorporates recommendations as core principles and they become
requirements later.
• R. Muckle asked for explanation of figures found on handout:
These were a cost estimate vs bid. Vendor stated they have not
underestimated a project.
• M. Blankenship asked if they have worked with hybrid companies with
adapting and merging into one:
They are currently working on that type of project.
• R. Tuneski asked how many design awards they have won:
This is not what they always aim for. They have be awarded 3 awards
for a building they were only trying to design as a cost effective,
durable building in very trying times.
Purchasing Agent B. Davy gave report on references:
• The Galante Architecture Studio
1. Good reference from Davenport
2. The design phase is 6-8 months behind in Cambridge, MA
• Silver, Petrucelli & Associates
1. Came in over budget on job
2. Stonington wants to hire them again – They have had no issues with
prior building, communicative
Committee members voiced their choice of vendor and reason for choice:
R. Bracciale: SP&A - Vendor is local and cost is significantly less
W. Gilpin: SP&A
T. Olynciw – Abstained
M. Blankenship – SP&A: Cost and local
P. Rafuse – SP&A
B. Sabilia – SP&A
J. Bracciale – SP&A: Local and architecturally pleasing
R. Muckle – SP&A: Team is all in one house, have good designs, local
R. Tuneski – SP&A: Local and examples have a large range
The committee favors selecting SP&A over TGAS.
In order to request additional funding at the Board of Selectman's meeting
scheduled for 1/9/24, the committee agreed to a special zoom meeting to be
held on 1/8/24 at 6pm. R. Tuneski will work with Attorney N. Kepple to
develop a memorandum to present at the 1/8/24 meeting.
R. Tuneski requested T. Holland work up the numbers of both architect
firms. Atty. N. Kepple is charged with confirming T. Holland's
calculations are reasonable.
Meeting adjourned at 8:50pm
Respectfully submitted by:
Linda Finnegan, Recording Secretary