WATERFORD UTILITY COMMISSION
DATE:
March 24, 2026
PLACE:
1000 Hartford Turnpike
PRESIDING:
Chairman Ken Kirkman
MEMBERS PRESENT:
Jerry Porter, Ryan Boyle and Ray Valentini
MEMBERS ABSENT:
Beth Sabilia
ALSO PRESENT:
J. Robert Tuneski, Board of Finance Liaison
Attorney Nicholas Kepple, Town Counsel
Staff: Jill Stevens, Director of Utilities
Shawn Matthews, Assistant Director of Utilities
Amy Windle, Office Coordinator/Recording Secretary
Chairman Kirkman called the meeting to order at 6:00 pm
CITIZEN SESSION-
None
SECRETARY’S REPORT
MOTION
Made by Mr. Valentini to approve the Minutes of January 13, 2025, Mr. Boyle
seconded.
VOTE
The motion passed unanimously.
BILLING ADJUSTMENTS
The Commission reviewed the January and February adjustments. The adjustment reports are
kept in the office for review.
EXPENDITURES
MOTION
Made by Mr. Valentini to approve the January and February 2026 bill lists, Mr.
Porter seconded.
VOTE
The motion passed unanimously.
Waterford Utility Commission
March 24, 2026
2 | P a g e
OLD BUSINESS
•
Financial Report
The financials for January and February were reviewed. Ms. Stevens reported that the
Treatment Cost line in the budget will be reviewed and increased in the next proposed
budget for FY27.
•
Collection’s Report
Attorney Kepple reported that his staff received 40 new files for collections. He also
discussed reviewing the policy on Judgment accounts in a couple of months.
•
Director’s Report
Ms. Stevens reviewed her report that provides updated information on all Utility
Commission Capital and Operational projects currently funded. A copy of the Director’s
Report will be attached to the minutes when posted.
Mr. Matthews reviewed the Asset Management report.
NEW BUSINESS
Sewer Rate Study
Ms. Stevens reported that Raftelis started the rate study in January and has met a few times to go over
questions regarding data provided to them by staff. The evaluation and analysis of the current rate
structure is complete, Raftelis would like to present their findings and recommendations to the
Commission at the April regular meeting.
Attorney Kepple recommended that a community presentation would be beneficial to answer questions
and received feedback from the Commission’s customer base prior to a public hearing that proposes any
rate changes.
Policy Manual Update
Ms. Stevens explained that the policy manual is in need of updating. There are policies that go back 20+
years and are no longer applicable to the organization. She provided Section 9000-Bylaws, which the
Commission needs to review and make changes. Attorney Kepple offered his assistance in drafting new
polices.
WATER
City of New London/Veolia Report.
The Commission reviewed the report. Ms. Stevens reported that drought restrictions might be possible
in the summer based on current and projected reservoir levels.
Water Agreement Working Group Update
Ms. Stevens and Commissioner Valentini proposed a few strategies for the Commission to consider that
would enable the group to work on the Interlocal water agreement after the disbanding of the Water
Working Group. A special meeting will be scheduled in April to bring the Commissioners up to speed on
the history of past Water Agreements, especially as there are new members on the Commission. In
Waterford Utility Commission
March 24, 2026
3 | P a g e
addition, a draft report completed by Resilient Water and Land was provided for the Commission’s
review.
CORRESPONDENCE
•
Reimbursement Request made by 43 Miner Ave for a plumber’s bill to camera his
private building sewer. The resident did not contact the Utility Commission office for
assistance to determine whether a suspected clog was located on private property or
within the Town’s system. The Department does have a camera truck and could have
done the work. A root ball/obstruction was found to be within the Town’s right of way;
one of the Utility Commission’s on call contractors removed the obstruction and
repaired the sewer lateral within the Town’s right-of-way to correct the issue.
MOTION
Made by Mr. Porter to deny this request based on past practices,
seconded by Mr. Boyle.
VOTE The motion passed unanimously.
•
Minutes from East Lyme and Old Lyme
•
Wright Pierce-Update on Contract One Project.
•
Memo from the Ethics Commission
•
Resilient Land & Water-Draft of Interlocal Water Agreement
PLANS REVIEW –
850 Hartford Turnpike: Crystal Mall Adaptive Reuse Plans were presented
PERSONNEL
Sewer Tech I position is still vacant.
Account Receivables Clerk, the current A/R Clerk has tendered her resignation effective March 27, 2026.
The opening was posted internally, there was one internal applicant an interview is scheduled for March
25.
Ms. Stevens proposed that the wastewater billing be outsourced to InHance, the current billing software
vendor, for up to three months due to internal accounting controls that prohibit one employee from
both billing and collecting payments until a suitable candidate is hired.
MOTION
Made by Mr. Valentini to allow the wastewater billing to be outsourced to
InHance for 3 months for up to $5,000 a month, seconded by Mr. Boyle.
VOTE
The motion passed unanimously.
OTHER
ADJOURNMENT
With no further business before the Commission, the meeting adjourned at 8:01 p.m.
Waterford Utility Commission
March 24, 2026
4 | P a g e
MOTION
Made by Mr. Boyle to adjourn, Mr. Porter seconded.
VOTE
The motion passed unanimously.
Respectfully submitted,
Amy Windle
Recording Secretary
P a g e | 1
Waterford Utility Commission
Director’s Report
March 24, 2026
This report summarizes the Commission’s ongoing projects and operational activities as of 3/20/26
Current Capital and Capital Non-Recurring Funded Projects
1. Inflow and Infiltration Mitigation and Control
FY 19 Capital Non-Recurring Expenditure Fund L.I. #20531-57685
Original Appropriation: $388,303.00 Available Balance: $235,865.56
This is an ongoing project to identify sources of Inflow and Infiltration within the Richards Grove Sewer
Basin.
Current Project Status: No change to this project this month. Waterford crew continues to install
manhole dishes within the wastewater basin as time permits, flow monitoring will be conducted again
after all manhole dishes have been installed to determine if surface runoff is the majority source of the
inflow. Richards Grove SSES – Wright Pierce will assist with recommendations for future flow monitoring
in the spring of 2026.
Project Background: The Richards Grove Road Wastewater Basin Inflow & Infiltration (I&I) evaluation
being conducted by Wright-Pierce Engineers for $27,500.00. This project consists of conducting I&I
evaluations and a Sewer System Evaluation Study (SSES). This drainage area has been identified as one of
the larger contributors of I&I to our Collection System. This area possesses approximately 5 miles of 8-
inch diameter gravity sewer piping and serves primarily residential users. The current flows received and
conveyed by the Richards Grove Pump Station are greater than the capacity of the pump station,
triggering the potential need for a capacity upgrade if the I&I sources cannot be identified and mitigated.
The I&I mitigation and control program is an ongoing project. Our staff routinely conducts pipeline and
manhole assessments with the use of our CCTV and Jet Rodding apparatus. Deficiencies are located,
graded and catalogued based upon severity. Corrective repairs are typically conducted during springtime
utilizing robotic trenchless technology.
2. Old Norwich Road Wastewater Pump Station Rehabilitation
There are two CNR designations totaling $1,299,369 in L.I. # 20531-57816.
In addition, available ARPA funds have been increased to $1,341,316 per finance as of June 4, 2025.
Original ARPA funds available were in the amount of $1,020,041.
Current Project Status: Construction in progress. Pump startup occurred on March 6 and removal of
bypass pump system occurred on March 13, an all-day crew training session is scheduled for March 25,
P a g e | 2
2026 in anticipation of the Utility Commission taking ownership of the station on March 27th and a
completion date of April 30, 2026 based on recent progress.
Project Background: This project entails an upgrades needed to replace aging equipment at the Old
Norwich Road pump station. The upgrades include the replacement of the three sewage pumps and
associated piping and valves and the installation of a new bypass pumping connection. Comprehensive
upgrades will also be performed for the electrical systems including replacement of conduit and wiring
and the electrical distribution and pump control systems. The ventilation system will also be
replaced. Painting and minor architectural improvements will be performed to replace the exterior
doors, louvers, trim and roof. Competitive bid results for this project were received on August 10, 2023.
The lowest bid received was from Holzner Construction in the amount of $2,113,850.00 The Notice to
Proceed for Holzner was executed on January 16, 2024. A Contract Administration proposal from Wright-
Pierce was executed 1/19/2024 in the amount of $55,800.00 an anticipated completion date was
expected about November 2025, however the contractor has provided an updated final completion date
of 2/11/2026.
3. Control Panel Retrofit
FY22 Capital Improvement Fund L.I. # 33122-55894
Original Appropriation: $30,000.00 Available Balance: $0 – line closed
Current Project Status: No change to this project in the last 30 days, this project will resume when as we
complete the build phase on the SCADA project.
Project Background: This project entails replacing the existing pump control panels, which are obsolete
and unsupported with current control technology. This work will ensue upon completion of upgrades
currently being conducted at 10 of the lift stations, which are identified within this report and are being
funded with ARPA funds.
4. Gorman-Rupp Pump Station Controls
This is an ARPA allocation project in the amount of $163,750.00. L.I. # 23531-55013
Current Project Status: Some progress has been made at Ridgewood Ave, after replacing the pumps in
early December, we are installing the remaining screens and completing the electrical work in
conjunction with the SCADA project. The station will be placed on by-pass during the day and returned to
normal operation at night for two days to complete the remaining electrical work that requires de-
energizing of the pumps.
Project History: To date Shore Road, Dock Road, Richards Grove Road, Old Barry Road, Quaker Hill
Center, Oil Mill, Oswegatchie Rd and Niantic River Road stations are complete. Ridgewood Ave station, is
the last station for this project and is nearly complete, all that remains is some work on the dry side in the
station, this work will resume now that the safety consultant has completed his evaluations and
additional gear has been procured.
Project Background: Utility Commission staff is performing the installation of equipment, conduits and
wiring. A scope of services change order was executed that directs the contractor to supply 18 cellular
amplifiers and associated equipment in lieu of providing broadband to 5 stations. Utility Commission staff
will be installing the amplifiers during the process of the controls upgrades. This project is ongoing.
5. Pump Station Exterior Improvements
FY22&23 Capital Improvement Fund L.I. # 33123-55895
Original Appropriations: $ 100,000.00 (50K ea. L.I.) Available Balance: $16,719.48
Current Project Status: No change to this project this month. The crew continues regular exterior
maintenance work at all the stations including landscape upkeep. We have identified four stations that
need new roofs, and have taken precedence over a new driveway at Cross Road. Due to staffing
shortages this project has been delayed until the summer of 2026.
P a g e | 3
Project History: To date under these two L.I.#s, roof replacements have occurred at Shore Road, Dock
Road, Bolles Ct, Waterford Village, Sea Side, Niantic River Rd, Mago Pt and Evergreen Ave stations. The
exterior siding was replaced at the Waterford Village and Bolles Ct stations. Siding repairs were
conducted at Stoney Brook Station. A new asphalt driveway was installed at the East Neck pump station.
6. Contract #1 Sewer Easement Access Project
Capital Improvement Fund L.I. # 33123-55019 & FY26 CNR L.I. # 20531-57894
Original Appropriation: $250,000.00 & Additional Designation: FY26 CNR $200,000
Available Balance $285,989.63
Current Project Status: Advanced Resources began construction on December 10, 2025, site work in
progress, all the hand clearing and brush removal is complete, removal of the larger trees and final clean
up remains, due to wet ground conditions after the snowmelt we anticipate the contractor will be able to
resume work in a week or two. The project is on track to be completed on time. A task order for a not to
exceed fee of $41,000 was received and signed on March 20, 2026 for the final design drawings and bid
services to complete Phase 2. This will enable us to go out to bid for the remainder of the interceptor in
the near future. We have engaged legal counsel’s assistance to obtain the two easements needed to
complete the second phase, easement maps and descriptions are included in the scope for design with
Wright Pierce. A construction field report is included in your packets from the February meeting.
Project Background: Contract #1 was the Town's very first sewer construction project, which began in
1970. This project entailed the installation of approximately 13,000 linier feet of sewer main. A Special
Appropriation in the amount of $250,000 for engineering services was appropriated for the Contract #1
Sewer Main Access project in 2023. Survey work to identify the Contract #1 easement area, manholes,
intersecting property lines, and other utilities within the easement area commenced in October of 2023
and was completed in the spring of 2024. The final design package (drawings and specifications) to be
used for contractor bid solicitation and construction for Phase One of the restoration project was
approved by the Utility Commission at the November 2024 meeting. Phase one encompasses the
southern section of the interceptor beginning at the intersection of Great Neck Road and Rope Ferry
Road to the end of the interceptor at Evergreen Avenue Pump Station. Phase two which encompasses
the northern section of the interceptor from Boston Post Road to Great Neck Road requires the
acquisition of additional easements to gain access to the interceptor during restoration and for the Utility
Commission staff in the future. Splitting the project into two Phases allows restoration work to begin
while easements are procured, so that once Phase one is complete easements will be in place and Phase
two can begin shortly thereafter.
7. Plastic Water Service Line Replacement Program
CNR Appropriation L.I. # 20531-57881
Original Appropriations: $550,000.00 + $181,300.00 = $731,300.00
Additional Designations: $200,000 total in FY24 & FY25 ($100K each year), & $500,000 in FY26 GFB
Available Balance: $784,748.62
Current Project Status: The crew has begun material identification on the District 2 roads identified by
DPW’s current paving plan. We continue to work closely with DPW to ensure we are meeting their
pavement schedule. The crew and our equipment needs to be used to clean & camera the wastewater
system this summer, therefore, we anticipate going out to bid for the replacement of these services this
year at the end of the month, or first week in April with an accurate count of all services requiring
replacement. In FY26 the DPW’s updated paving plan has identified several roads scheduled to be
repaved, within these roads lie approximately 376 water services, of those approximately 165 may need
to be replaced, as the material type is unconfirmed. The WUC maintenance crew completed material
type identification on DPW’s FY26 paving program roads in District 3. We will be working on the roads
P a g e | 4
impacted by Eversource in Quaker Hill to determine material types and plan for replacements beginning
in early 2026, as we continue our goal to remain one full year ahead of DPW’s paving program.
Project Background: There are approximately 7900 water services in Town, many of which are plastic and
have exceeded their useful life resulting in unaccounted for water loss and degradation to the Town
roads. The goal of this program is to replace the aging plastic water services with copper line prior to
DPW paving the roads. Since the start of this cooperative project with DPW 806 water service lines have
been investigated, of those 229 water service lines were found to be plastic and replaced totaling 5,218
linear feet. Service line replacement costs are on average $4100 each depending upon the service line
length and location, typically we are finding about 30 percent of the unconfirmed service material types
are plastic and require replacement.
8. Bartlett Corners Booster Station Decommissioning
CNR Designation L.I. #20531-57896
Original Appropriation: $166,950
Current Project Status: Haley Ward’s task order for a lump sum of $22,705 was reviewed by staff and is
awaiting signatures to begin the project.
Project Background: In 2006, the Town constructed water system improvements that enhanced water
pressures and fire flows to the Quaker Hill area of Waterford. Included in this project were a new 2500
gpm capacity water booster pumping station near the intersection of Old Colchester and Old Norwich
Roads, and a 1.5 million gallon pre-cast, pre-stressed concrete water storage tank constructed on Rogers
Hill. From 1977 up to 2006, the Bartlett Corners Hydro-pneumatic Station served a small high service area
on a hill in the northeast corner of Waterford consisting of approximately 20 residential customers on
Lathrop Road, Lower Bartlett Road, Upper Bartlett Road, Pepperidge Road and South Bartlett Road. Once
the new Quaker Hill water system improvements were activated in 2006, the Bartlett Corners Station was
inactivated however not fully decommissioned. In 2009 a decommissioning report was prepared which
identified costs of $105,000 to properly decommission the station. This project has been identified within
previous CIPs. Utilizing the Engineering News Record’s Construction Costs Index inflation factor of 1.59
from 11/2009 to 11/2024, the current decommissioning costs estimate is $166,950.
9. Water Tank Asset Management Program
CNR Appropriation L.I. # 20531-57895
Original Designation: $46,222
Available Balance: $2,726.00
Current Project Status: This project is complete for this year, the Commission will be updated as routine
inspections are performed and inspection reports provided. The project will be removed from this report
after this month.
Project Background: The Town of Waterford owns three water storage tanks, the 750,000 gallon Fargo
Tank, the 300,000 gallon Vauxhall tank and the 1.25 Million gallon Rogers Hill tank. In 2024 the Fargo
Road Tank refurbishment project was completed; prior to this renovation, the Fargo Road water tank had
its original coat of paint, which had far exceeded its useful life expectancy by approximately 10 years. This
work was necessary to preserve the Town’s significant investment in its infrastructure and to extend the
life of its asset. A Water Tank Management Program for these valuable assets would preserve the
significant investment the Town has made in water storage tanks by guaranteeing routine inspections
and maintenance of the water storage tanks does not fall behind, thus improving the reliability of the
system. A sustainable water tank management solution also makes budgeting easier as initial repair costs
can be spread out over a few years if necessary and all future interior and exterior renovation costs are
included. Our intent is to initiate a funding schedule that would enroll the three water storage tanks in a
Tank Asset Management program progressively, beginning with Fargo Road in FY26, this tank will not
require any Upfront Renovation costs to enroll in the program, only annual Maintenance plan costs.
P a g e | 5
Sewer Development & Maintenance Fund Projects
10. SCADA System Upgrade Design/Build
L.I. # 24431-57766
Approved Task Order: $147,600.00 + $19,200 change order in March: $166,800
Current Project Status:
The Zero Tunnel Network issues have largely been resolved, we are awaiting a change to the IP address
scheme for the station routers due to a conflict with the RF IP addresses that was not identified by the
Wright Pierce design team. This change, however, is not holding up deployment of Ignition. Wright
Pierce’s build team and Jeff Robillard began configuration of the system on March 17th on site and will
continue this work in the next two weeks. We will run both Wonderware and Ignition side by side for
approximately two weeks to ensure all the existing radio alarms are functioning on Ignition in the same
way as they currently function with Wonderware. Once that test is complete Wonderware will be
decommissioned. The cellular network deployment will continue on a parallel track, but is not critical to
the deployment of Ignition.
Project Background: The current SCADA (Supervisory Control and Data Acquisition) system has
experienced multiple failures over the past several months, which has necessitated calling in the entire
crew to canvas the pumps stations on at least one occasion while the system was brought back online;
additionally two different software programs used to operate the system are no longer supported and
the hardware has exceeded its useful life. The Commission has entered into a design-build contract with
Wright Pierce, our on-call engineering firm, to replace the failing system. The new system platform will be
Ignition, a software system found and piloted by one of our current Maintenance Operators and
presented to the Commission over the past few years. Additionally the communication between stations
to the maintenance shop/Municipal Complex will be accomplished over a closed zero-tunnel cellular
network with radio redundancy. The Commission approved the proposal from Wright-Pierce for this
project in August of 2024, the cellular network work is outside of this proposal and is being handled by
Utility Commission staff. An amendment was discussed at the December meeting with a representative
from Wright-Pierce and involved avoiding duplicative efforts in terms of IT infrastructure/resources that
the Town could provide the Commission, including options for fiber connectivity, data storage, and
virtualized hosts. A final amendment to the scope of the project was received on March 26, 2025 after
much discussion, an addition to the scope was made to host a documentation management portal for
ease of management for all Utility Commission documentation moving forward. The total cost for the
change of scope is an additional $19,200 to their original approved task order and a timeline extension of
6-8 weeks as a result of the agreed upon scope changes. The changes to the scope will net long term
savings to the Commission over the life of the SCADA system due to the elimination of the $2,000
monthly cost for a separate fiber internet connection which over an anticipated 7 year life of the system
equates to a cost savings of over $150,000 in internet connection fees alone, amongst other reoccurring
costs for data storage and back up.
11. Water and Wastewater Standards and Specifications Update
L.I. # 24431-52121
Approved Task Order: $36,800.00
Available Balance: $23,035.74
Current Project Status: Two working sessions with Waterford and New London staff were held on
12/9/25 and 1/7/26 to review the W-P draft standards and specifications provided. The final working
session scheduled in January had to be rescheduled due to weather events twice and is now set for
Wednesday March 25th. The results (redlines) of the working sessions will be provided to Wright Pierce to
incorporate into the next draft of standards and specifications. We anticipate one or two more working
sessions with New London to confirm the changes and provide any additional feedback before accepting
the new standards and specifications to be published.
P a g e | 6
Project Background: The current Water and Wastewater Standard and Specifications the Utility
Commission uses are significantly outdated and require updating. This project is being cost-shared with
the City of New London.
Other Utility Commission Updates
•
Resilient Land and Water has provided a draft white paper summarizing the review of the Commission’s
historical files, this will be included in your paper packets.
•
Flow metering – EST completed all the updates and installation to the flow meters used for Interlocal
billing, an online portal is active and reports are being generated by EST to provide us with monthly flow
data. The work completed included relocating one meter from Boston Post Road to Mago Point, installing
a battery powered Dura-Tracker logger at Boston Post Road, installing a new area velocity sensor at
Evergreen, adding modems and antennas on all the meters to enable communication to the Cipher
telemetry program for data management and reporting.
Respectfully Submitted,
Jill N. Stevens
Director of Utilities