TOWN OF WATERFORD
COASTAL SITE PLAN REVIEW
WRITTEN FINDINGS & DECISIONS
cr. 1801 S
ORIGINAL TO: COASTAL SITE PLAN REVIEW TRIGGER:
James Bernardo, LS [_] Zoning Compliance (Site Plan)
Waterford, CT 06385 L] Special Exception or Permit
{Bl Variance
[_] Municipal Improvement
APPLICANT NAME: Maryse Callard Trustee, C/O George Szdlowski
MAILING ADDRESS: P.O, Box 422, Goshen, CT 06756
PROJECT ADDRESS: , ,,.
4 Ridgewood Avenue
PROJECT DESCRIPTION:
The construction of a single family house elevated on a pile support system located at 4 Ridgewood
Avenue.. The proposed structure is approximately 852 sq. ft located on an existing vacant residential lot
of 10600 sq. ft in a VR-7.5 Zoning District. The rear of the lot is bounded on the East side by Alewife
Cove, on the North by a Town of Waterford Sewer Pump Station and the South by a residential
dwelling. Tidal Wetlands occur on the southern and eastern portion of the lot. The State of Connecticut
Coastal Jurisdiction Line extends within the property from its boundary with Alewife Cove.
The entire parcel is located within FEMA designated Special Flood Hazard Areas VE (El-13) and AE
(El-10). The applicant proposes to construct the house in accordance with design standards for
residential buildings within VE Flood Zones. The property is served by municipal water and sewer. The
applicant has applied for varainces to the front and sideyard setback requirements for which the Town
of Waterford Zoning Board of Appeals will review as well as the CAM application.
Plan title: "Zoning Compliance Survey, Property of Maryse Callard, Trustee for property
located at 4 Ridgewood Avenue, Town of Waterford — County of New London —
Connecticut" Dated April 21, 2023
#ZBA-23-5
4 Ridgewood Ave
Exhibit 11

Coastal Site Plan Review Comment Checklist
Page 2
COASTAL RESOURCES AND RESOURCE POLICIES:
General Coastal Resources*
Beaches and Dunes
Bluffs and Escarpments
Coastal Hazard Area
Coastal Waters and/or Estuarine Embayments
Developed Shorefront
Freshwater Wetlands and Watercourses
Intertidal Flats
Islands
Rocky Shorefront
Shellfish Concentration Areas
Shorelands
Tidal Wetlands
ON-SITE
cy
HOOOOOOORBKROOSGA
ADJACENT POTENTIALLY
TO SITE INCONSISTENT
OD O
Oo O
O O
Oo O
oO O
Oo O
oO oO
oO oO
Oo O
NoT
APPLICABLE
OOSS8BHBABRAOOSSRO
ADVERSE IMPACTS ON COASTAL RESOURCES:
COASTAL USE POLICIES:**
Acceptable
Degrades tidal wetland,
beaches and dunes, oO
rocky shorefronts, or
bluffs and escarpments
Degrades existing
circulation patterns of Oo O
coastal waters
Increases coastal im] oO
flooding hazard by
altering shoreline or
bathymetry
Degrades natural or
existing drainage im
patterns
Degrades natural
shoreline erosion and O
accretion patterns
Degrades or destroys oO
wildlife, finfish, or
shellfish habitat
Degrades water quality Oo oO
Degrades visual quality Oo oO
Appears. Potentially
Unacceptable
Not
Applicable
QO
iS
E
rs)
General Development*
Boating
Coastal Recreation and
Access
Coastal Structures and
Filling
Cultural Resources
Fisheries
Fuels, Chemicals, or
Hazardous Materials
Ports and Harbors
Sewer and Water Lines
Solid Waste
Transportation
Water-dependent Uses
Potentially
Applies __ Inconsistent
O
oO O
oO oO
O Oo
Oo O
O
O O
Oo O
Oo Oo
Oo O
Oo Oo
oO O
* General Coastal Resources and General Development policies are applicable to all proposed activities.
** Policies that are not applicable are not checked in this chart.

Coastal Site Plan Review Comment Checklist Page 3
ADVERSE IMPACTS ON FUTURE WATER-DEPENDENT DEVELOPMENT ACTIVITIES AND OPPORTUNITIES:
Appears Potentially Not
Acceptable Unacceptable Applicable
Replaces an existing water-dependent use with a non-water-dependent use oO oO
|
Reduces existing public access
iS
water-dependent use for which there is a reasonable demand
Locates a non-water-dependent use at a site that has been identified for a
Locates a non-water-dependent use at a site that is physically suited for a oO oO
water-dependent use in the plan of development or zoning regulations O O
ISSUES OF CONCERN (SEE SUMMARY AND RECOMMENDATIONS BOX FOR ADDITIONAL DETAIL):
Insufficient information
Potential increased risk to life and property in coastal hazard area
Adverse impacts on future water-dependent development opportunities
Proximity of disturbance to sensitive resources/need for additional vegetated setback
HRORO
Potential to cause erosion/sedimentation; need for adequate sedimentation and erosion control
measures
Water quality and/or stormwater impact
Other coastal resource impacts:
Other:
OOW
SUMMARY AND RECOMMENDATIONS:
The use of the property as a single family residential structure is consistent with the Town Zoning Regulations and
2012 Plan of Conservation and Development. The proposed house will be constructed within the FEMA designated
SFHA AE Elev 10. The Zoning Regulations require that the elevation of the first floor to be no less than 1 foot above
the designated Base Flood Elevation. The applicant proposes to construct the house utilizing a pier support system
and provide for a first floor elevation no less than 2 feet above the AE base flood elevation (BFE) of 10.
Potential to cause erosion/sedimentation; need for adequate sedimentation and erosion control measures:
The construction sequence indicates that all removed vegetation and unsuitable material shall be removed from the
site and that the only material stockpiled on the site will be topsoil. The stockpile shall be surrounded with erosion
controls consisting of silt fence backed with hay bales and temporarily seeded. The project as presented identifies the
proximity of site disturbance to the on-site tidal wetland. While this disturbance is of a temporary nature during the
construction of the single family dwelling and the sensitivity of this resource, all erosion control silt-fence shall be
backed with haybales and remain in place until exposed soils have been permanently stabilized.
Water quality and/or storm water impact:
There is a potential for a temporary negative impact to water quality during the construction phase of the project. This
potential will be mitigated through the installation and maintenance of erosion control measures as identified on the
plan and within these recommendations.
Impacts from post construction storm water will be mitigated by locating the roof-water discharge to the northeasterly
side of the building, opposite and the furthest point from the tidal wetlands. The roof-water discharge will be captured
by rain barrels and allowed to overflow onto stone areas underneath the elevated building.

Coastal Site Plan Review Comment Checklist : Page 4
The proposal, as planned and presented, is consistent with stated Coastal Area Management policies
This project as approved with conditions 1 thru 7 is consistent with all applicable coastal policies and includes all reasonable measures to
mitigate adverse impacts.
1. The site plan as approved by the Zoning Board of Appeals shall be the plan submitted for Zoning Compliance/Building Permit review.
Any deviation from the approved site plan shall be reviewed by the Zoning Official. The Zoning Official reserves the right to determine
whether any proposed modifications will need to be submitted to the Planning and Zoning Commission for a modified site plan
approval.
Flood Hazard Design Compliance as required herein
2. The parcel is located within the FEMA designated Special Flood Hazard District AE and VE. The house will be constructed within the
SFHA AE. The proposed structure is to meet all requirements of Section 25.3 of the Zoning Regulations, Development in Flood Hazard
Areas including plans prepared by a licensed Architect and/or PE.
3. No work of any kind to take place below the Coastal Jurisdiction Line without additional permits from the
Town of Waterford and the Connecticut DEEP.
4. The plans note that in the case of a 100-year storm event there will not be dry access to or from the property.
5. Erosion control measures during construction shall be provided on site for the duration of the project and until the establishment of
vegetative cover on disturbed areas. A detail of the erosion control measures (silt fence w/ haybale) shall be provided n the site plan
prior to filing on the land records.
6. No work covered by this permit including the stockpiling of materials shall be conducted outside of the silt fence and limit of disturbance.
7. An as-built survey shall be submitted and approved by the Zoning Official prior to issuance of a Certificate of Zoning
Compliance. This requirement is to verify that all improvements have been constructed in accordance with the approved
site plan.
FINDING: (Please see summary and recommendations section on page 3 for discussion)
oO CONSISTENT WITH ALL APPLICABLE COASTAL POLICIES, COMMENTS INCLUDED
I} CONSISTENT WITH MODIFICATIONS OR CONDITIONS
oO ADDITIONAL INFORMATION NEEDED PRIOR TO COMPLETE CSPR EVALUATION
SUPPORTING DOCUMENTATION ATTACHED TO THIS CHECKLIST:
Copies of photographs of the site dated:
Copies of aerial photographs dated:
GIS maps depicting:
Coastal resources maps dated:
OLISP Fact Sheet(s):
OOoOaaodn
Other:

Coastal Site Plan Review Comment Checklist Page 5
Please be advised that, separate from the municipal review, the following
Department of Environmental Protection permits may be required:
LJ Structures, Dredging, and Fill in Tidal Coastal or Navigable Waters
C1 Tidal Wetlands
[1 Stormwater General Permit (construction / industrial / commercial )
LJ Other
For more information, contact:
copies provided to