DEPARTMENT OF PLANNING AND DEVELOPMENT
MEMORANDUM
TO:
Planning and Zoning Commission
FROM:
Mark Wujtewicz, Planner
DATE:
August 8, 2023
TITLE:
Staff Report: Chipotle Restaurant
122-124 Boston Post Road
PL-23-10
EXECUTIVE SUMMARY
The project as proposed is to implement the second phase of the Aldi’s Plaza Master
Design Plan with modifications. This project as proposed is to construct a 2,325 sf Chipotle
restaurant. The site is located within the PDD-1 (Planned Design District 1) Zone District for
which a Master Design Plan (MDP) indicating two phases for development of the parcel was
reviewed and approved by the Commission on May 23, 2016 through Application PL-16-3.
Subsequent to the PDD-1 approval, a site plan to implement the first phase of the MDP was
approved by the Commission on August 8, 2016 through application PL-16-11. This first phase
was for the construction and improvements to the site for the Aldi’s Grocery Market. The
original Master Design Plan Phase 2 proposal included the construction of two buildings of
8,100 sf and 4,320 sf for retail and restaurant respectively. This Phase 2 implementation
currently before the Commission is for the construction of a 2,325 sf Chipotle Restaurant and
associated site improvements including installation of new drainage and other utility
infrastructure, new landscaping and parking configuration. This proposal is a modification to the
Phase 2 improvements that were presented in the Master Design Plan.
BACKGROUND
Pertinent Regulations
CGS 8-3(g)
Section 30.1 – Planned Design District 1 (PDD-1)
Permitted Uses -1c) Restaurants
Section 22 – Site Plans
FIFTEEN ROPE FERRY ROAD
WATERFORD, CT 06385-2886
F:\PUBLIC\WS\PZAPPS\In Process\Boston Post Road, 122-124, PL-23-10\Draft Staff Report.docx
Section 22b – Design Review of Site and Building Requirements
This application was received by the Commission on June 27, 2023. Action on this
application is required by August 31, 2023, notwithstanding any extensions that may be
granted.
Staff provided to the applicant review comments from various Town agencies and in
response to comments, revised plans and reports were received July 27, 2023.
DISCUSSION
The project as presented is for the implementation of Phase 2 of the Master Design Plan as
modified for the parcel located within the PDD-1 Zone District. The development of Phase 2 as
presented is a modification to the original approved development. The original proposed
development of Phase 2 included the construction of two buildings and associated site work.
Phase 2 as modified is to construct one building, a Chipotle Restaurant and associated parking,
drainage and landscaping in support of the one building. A second building originally proposed
in Phase 2 will not be constructed thereby reducing the amount of building coverage and
potential traffic impact that would be generated from the multi-tenant building. The one building
proposed also affords more flexibility in locating the building on the property and providing
more landscaping which reduces the amount of impervious area. Minor modifications to the
existing parking for the Aldi’s Grocery Market is proposed for the overall parking layout for the
property. The existing bank and the parking associated with it will remain in its current
configuration.
The restaurant will provide both indoor and outdoor patio seating. There will also be a
digital order pickup window with a bypass lane to accommodate pick up orders only. This will
not be a conventional drive thru as there is no accommodation for ordering service.
The existing entrance to the property from the signalized intersection at Boston Post Road
will remain. Recent modifications to the signalization was completed by CT DOT to
accommodate signal timing and pedestrian crossings. A Trip Generation Review completed by
the applicant’s traffic engineer was submitted into the record. The review concluded that the
development of the Chipotle restaurant does not require any mitigation of traffic impacts and that
adequate parking exists for all uses on the property.
The property is currently serviced by municipal water and sewer. The proposed building
will connect to the existing system. The stormwater impacts from the additional impervious area
will be mitigated through the use of a “Stormceptor” Water Quality unit and subsurface
stormwater infiltration system. The existing drainage system on the site was designed in
anticipation of the addition of Phase 2 development. The stormwater drainage report submitted
into the record finds that the proposed drainage design for Phase 2 is consistent with the drainage
system design that was included in the Master Design Plan.
The Design Review Board reviewed this application on August 8, 2023 and forwarded a
positive report to the Commission.
F:\PUBLIC\WS\PZAPPS\In Process\Boston Post Road, 122-124, PL-23-10\Draft Staff Report.docx
RECOMMENDED ACTION
Based on the information provided, staff recommends the Planning and Zoning Commission find
that:
Findings:
1.
The application is for a use permitted subject to Site Plan approval, pursuant to
Section 30.1(Permitted Uses - Restaurant) of the Waterford Zoning Regulations.
2.
The Site Plan as submitted substantially conforms to the Master Design Plan for
development of Phase 2 as approved by the Commission in accordance with Permit
PL-16-3 and Section 19 of the Waterford Zoning Regulations.
3.
The application meets the criteria for site plan approval, pursuant to Section 22 of the
Waterford Zoning Regulations.
4.
This application has been reviewed by the Town of Waterford Design Review Board
in accordance with Section 22b of the Waterford Zoning Regulations and which
Board submits a positive report to the Planning and Zoning Commission
and that the Commission approve the proposal with the following conditions:
1.
Prior to issuance of a Certificate of Occupancy for the Chipotle building, the pollution
prevention and stormwater management plan shall be updated to include the
modifications as a result of the site improvements associated with Phase 2 as shown.
2.
Prior to issuance of a Certificate of Occupancy, as-built plans shall be provided.
3.
The approval of the site plan includes fire zones as may be established and enforced
pursuant to Chapter 8.08 of the Waterford Code of Ordinances.
Proposed Motion
To approve with modifications the site plan Phase 2 Development for Chipotle Restaurant
application #PL-23-10 at 122 & 124 Boston Post Road with conditions 1 thru 3 and adopt
the findings 1 thru 4 of the staff report.