Civil Engineers & Land Surveyors, P.C.
BY: MJO .
DATE: 5-1-24 .
SUBJECT: Williams School Athletics Team / Maintenance Building . SHEET No.: 1 OF 1 .
CHECKED: LJM . DATE: 5-1-24 .
Water Quality and Required Retention Volume Design Computations . PROJECT No.: 23-43 .
Summer Hill
1. Water quality volume and required retention volume computed using the CT Stormwater Quality Manual equation
WQV = RRV = (1.3)(R)(A)/12, where:
WQV, Water quality volume (cubic feet)
RRV, Required retention volume (cubic feet)
P, Precipitation depth = 1.3 inches
R, Volumetric runoff coefficient = 0.05 + 0.009(I)
I, Post-development impervious area (percent)
A Post-development site drainage area (square feet)
I = 44.0%
R = 0.05 + 0.009(44.0) = 0.45
A = 27,030 ft2
WQV = RRV = (1.3 in)(R)(A)/12 = (1.3 in)(0.45)(27,030 ft2)/12 = 1,318 ft3
2. Stormwater basin storage volume
Elevation
ft
Area
ft2
Average Area
ft2
Incremental
Volume
ft3
Cummulative
Volume
ft3
Cummulative
Volume
Ac-ft
80.50
1,010
1,010
0
0
0
81.00
1,035
1,023
511
511
0.0117
82.00
1,405
1,220
1,220
1,731
0.0397
Remainder of this page left blank