Conservation Commission Regular Meeting Materials (linked)
agenda center agenda
| Board/Commission | Conservation Commission |
|---|---|
| Meeting Date | December 08, 2022 |
| Pages | 3 |
| File Size | 0.3 MB |
| OCR Status | Searchable (OCR processed) |
| Source URL | Original |
Document Preview
Full Text (OCR Extracted)
Waterford Conservation Commission Inland Wetlands & Watercourses Permit #C-22-13 314 Rope Ferry Road, Waterford, CT The Waterford Conservation Commission, in their capacity as the Town’s Inland Wetland Agency, herein authorizes the applicant to conduct regulated activities in designated areas at 314 Rope Ferry Road, Waterford, CT which are subject to the jurisdiction authorized by the CT General Statutes Section 22a-36 through 22a-45 inclusive, as amended, and the Town of Waterford Inland Wetlands and Watercourses regulations. This permit is a grant of approval, with conditions, in accordance with the Waterford Inland Wetlands and Watercourses regulations to conduct the following activities: 1. Clearing, fill and grading of 0.7 acres of upland review area to construct a 24 ft. wide paved access drive from the main entrance road east to the Eversource switchyard, south of the railroad. These regulated activities are associated with site modifications at 314 Rope Ferry Road, Waterford, Connecticut as depicted on a site plan entitled; “Proposed Driveway Plan, Prepared For Millstone Power Station, Rope Ferry Rd., Waterford, Connecticut”, dated 10/28/2020, prepared by Jones Engineering, LLC. The Conservation Commission has reviewed the application materials and attaches the following conditions to minimize impacts associated with the regulated activity and protect the inland wetlands and watercourses on this site: SPECIAL CONDITIONS: 1. The limits of clearing and disturbance shall be marked at the site and approved by the Commission’s agent prior to the start of site clearing and grading activity. 2. Temporary sediment controls shall be installed at the limit of fill slope along the access road as shown on the site plans prior to the start of fill and grading operations. 3. Upon completion of fill and grading, all driveway sideslopes shall be seeded and mulched, and covered with temporary erosion control blanket. 4. The permittee shall coordinate an inspection of the regulated activity upon completion of the finished grading to review erosion control measures and slope stabilization. Additional soil stabilization measures may be required. 5. Fueling of equipment shall not be conducted within the 100 ft. upland review area of inland wetlands and watercourses. Waterford Conservation Commission Permit #C 22-13: 314 Rope Ferry Road Page 2 of 3 STANDARD CONDITIONS: 1. The Conservation Commission’s agent shall be notified at least 48 hours prior to commencement of any regulated activity. 2. Final stabilization of disturbed soil areas shall be stabilized with the application of loam, seed and appropriate erosion control measures. 3. At all times during site work and until soil areas are stabilized, the applicant shall install and maintain erosion and sediment control measures such as fabric filter fence, staked hay bales or other measures deemed necessary by the Commission’s agent to prevent erosion and sedimentation impacts to wetlands and watercourses. 4. Erosion control and soil stabilization measures shall comply with the approved plans and the guidelines as established in the Connecticut Guidelines for Soil Erosion and Sediment Control, 2002, CTDEP Bulletin 34. 5. Upon direction of the Commission’s agent, erosion and sediment control measures shall be removed by the applicant following stabilization of the site. All work and all regulated activities conducted pursuant to this authorization shall be consistent with the terms and conditions of this permit. Any other construction, excavation, deposition of fill, obstructions of flow, encroachments or other regulated activities not specifically identified and authorized herein shall constitute a violation of this permit and may result in permit modification, suspension or revocation. In the event that any additional wetland or watercourse regulated activities are required as a result of other agency permitting to support the proposed facility, the Waterford Conservation Commission reserves the right to reconsider the regulated activities associated with the proposal and may require design modifications to minimize impacts to wetland and watercourse resources. In evaluating this application, the Commission has relied on information provided by the applicant. If such information subsequently proves to be false, incomplete and/or inaccurate, this permit may be modified, suspended or revoked. This permit shall be valid for a period of 5 years. Permit extensions may be authorized in accordance with CT General Statutes 22a-36 through 22a-45 inclusive. If the regulated activity is not completed within this time frame, the permit may be held to be invalid by the Commission and the applicant may be required to petition the Commission for an extension or re-issuance of the permit. The Commission may require the applicant to furnish additional information at that time. The Conservation Commission renders this Summary Ruling in accordance with the Waterford Inland Wetlands and Watercourses Regulations based on the following considerations: A. The activity does not involve direct or indirect impacts to inland wetland and watercourse resources. B. The short-term impacts of the activity will be controlled by application of erosion and sediment control measures. Waterford Conservation Commission Permit #C 22-13: 314 Rope Ferry Road Page 3 of 3 This permit will be strictly enforced. If the Conservation Commission finds that the applicant has not complied with the permit conditions or has exceeded the scope of this permit as set forth herein, or, if the intended use of the general site is not as represented by the application or the plan of record, the Commission may suspend or revoke this permit, direct the Environmental Officer to issue a cease and desist order, require the applicant to modify, extend or revise the site work, or require the applicant to restore the area to its original condition. Dated: December 8, 2022 Issued By: ________________________ Chairman, Richard F. Muckle Waterford Conservation Commission