WATERFORD UTILITY COMMISSION
DATE:
July 8, 2025
PLACE:
1000 Hartford Turnpike
PRESIDING:
Chairman Ken Kirkman
MEMBERS PRESENT:
Ryan Boyle, Tom Dembek, and Ray Valentini
MEMEBERS ABSENT:
Jerry Porter
ALSO PRESENT:
J. Robert Tuneski, Board of Finance Liaison
Attorney Nicholas Kepple, Town Counsel
Staff: Jill Stevens, Director of Utilities
Shawn Matthews, Assistant Director of Utilities
Amy Windle, Office Coordinator/Recording Secretary
Chairman Kirkman called the meeting to order at 6:00 pm
CITIZEN SESSION-
None
SECRETARY’S REPORT
MOTION
Made by Mr. Valentini to approve the Minutes of June 10, 2025, Mr. Boyle
seconded.
VOTE
The motion passed unanimously.
BILLING ADJUSTMENTS
The Commission reviewed the June adjustments. The adjustment report will be kept in the
office for review.
EXPENDITURES
MOTION
Made by Mr. Dembek to approve the June 2025 bill list, Mr. Valentini seconded.
VOTE
The motion passed unanimously.
OLD BUSINESS
Waterford Utility Commission
July 8, 2025
2 | P a g e
•
Director’s Report
Ms. Stevens reviewed her report that provides updated information on all Utility
Commission Capital and Operational projects currently funded. A copy of the Director’s
Report will be attached to the minutes when posted.
Mr. Matthews reviewed the Asset Management report.
•
Collection’s Report
Attorney Kepple explained the difference between Judgement and Foreclosure actions
through the courts and the impacts it has on the Utility Commission’s ability to collect
past due amounts when liens have been filed. He would like the Commission to
consider pursuing Foreclosures in place of Judgments to protect the Commission’s lien
position. If the Commission decides to follow Attorney Kepple’s suggestion, the
Commission should establish a dollar amount threshold that would commence
foreclosure proceedings when an account exceeds that figure. He would like to revisit
this subject at next month meeting.
•
Financial Report
The financials for May were reviewed.
NEW BUSINESS
WATER
City of New London/Veolia Report.
The Commission reviewed the report.
Water Agreement Working Group Update
Mr. Valentini reported that Ms. Stevens is in the process of securing funding to hire an engineering firm
to complete an engineering study to evaluate the Town’s Capital requirements related to the potential
renewal of the Waterford New London Interlocal Water Agreement.
CORRESPONDENCE
1. OSHA Informal Settlement Agreement
2. Request to the Board of Selectmen to re-designate existing capital funds currently appropriated
for the Old Norwich Road Wastewater Pump Station project into a new capital account for
engineering services related to the capital requirements surrounding the potential renewal of
the Waterford New London Interlocal Water Agreement.
PLANS REVIEW –
No plans
Waterford Utility Commission
July 8, 2025
3 | P a g e
PERSONNEL
An existing Sewer Tech II has been promoted to Sewer Maintenance Operator creating an opening for
Sewer Tech II to be filled, the position is currently posted.
OTHER
ADJOURNMENT
With no further business before the Commission, the meeting adjourned at 7:10 p.m.
MOTION
Made by Mr. Dembek to adjourn, Mr. Valentini seconded.
VOTE
The motion passed unanimously.
Respectfully submitted,
Amy Windle
Recording Secretary
P a g e | 1
Waterford Utility Commission
Director’s Report
July 8, 2025
This report summarizes the Commission’s ongoing projects and operational activities as of 7/2/25
Current Capital and Capital Non-Recurring Funded Projects
1. Inflow and Infiltration Mitigation and Control
FY 19 Capital & Non-Recurring Expenditure Fund L.I. #20531-57685
Original Appropriation: $388,303.00 Available Balance: $232,645.73
This is an ongoing project to identify sources of Inflow and Infiltration within the Richards Grove Sewer
Basin.
Current Project Status: As of 7/2/2025, an updated report with additional information from our CCTV
video review, flow meter data analysis and water usage data will be provided to Waterford July 3rd.
Waterford crew continues to install manhole dishes within the wastewater basin.
Project History:
As of 6/4/2025, Waterford and Wright-Pierce have been working together to assimilate recent CCTV
footage from 2025 plus flow meter and water use data to update the draft report from October
2024. Wright-Pierce and Waterford staff also performed a walk -down of the collection system on May
22nd after rainfall to check on ponding/pooling around vented manhole covers. An update report will be
provided to assimilate the more recent information into the draft report. Wright Pierce has reviewed the
recent flow meter and CCTV data provided. Flow graphs and spreadsheet provided with the observed
defects. Will review with Waterford and develop recommendations where to move the flow meter
and/or further studies. Additionally four manhole dishes have been installed during storms in direct
storm water flow paths in conjunction with manhole inspections in the basin. A draft report was emailed
on October 30, 2024 for review and comment; staff reviewed and issued comments back to Wright Pierce
to address within the report. Waterford has received their flow meters back from calibration. Flow
meter data will be used to determine next location for flow meters. Field data and video review and
QA/QC will be completed by Friday, September 13, 2024 with a target date of September 27th for the
draft report. No major manhole defects were noted. All field testing is completed (manhole inspections,
smoke testing). Wright Pierce is reviewing the field-testing results and working a Technical
Memorandum with the results. Manhole inspections were conducted on July 15 followed by Smoke
testing of the sewer mains on July 16th.
P a g e | 2
Project Background: The Richards Grove Road Wastewater Basin I&I evaluation being conducted by
Wright-Pierce Engineers for the amount of $27,500.00 This project consist of conducting inflow and
infiltration I&I evaluations and Sewer System Evaluation Study (SSES) . This drainage area has been
identified as one of the larger contributors of I&I to our Collection System. This area possesses
approximately 5 miles of 8-inch diameter gravity sewer piping and serves primarily residential
users. The current flows received and conveyed by the Richards Grove Pump Station are greater than
the current capacity of the pump station, triggering the potential need for a capacity upgrade if the
I & I sources cannot be identified and mitigated. The I&I mitigation and control program is an ongoing
project. Our staff routinely conducts pipeline and manhole assessments with the use of our CCTV and Jet
Rodding apparatus. Deficiencies are located, graded and catalogued based upon severity. Corrective
repairs are typically conducted during springtime utilizing robotic trenchless technology.
2. Old Norwich Road Wastewater Pump Station Rehabilitation
There are two CNR designations totaling $1,299,369 in L.I. # 20531-57816.
Available CNR Balance: $160,595.91 (including encumbrances)
In addition, available ARPA funds have been increased to $1,341,316 per finance as of June 4, 2025.
Original ARPA funds available were in the amount of $1,020,041.
Current Project Status: The contractor has provided an updated final completion date of 2/11/2026
based on the information available from the electrical supplier. However, some items are still not
received and could impact final completion. The contractor has installed temporary power for
construction (coordinated with Eversource). Contractor submitted updated bypass pumping plan, which
is being reviewed by Wright-Pierce.
Project History: Contractor is still waiting for confirmation of electrical gear delivery from
supplier. Supplier is unable to provided firm delivery schedule.
Contractor is proposing a 2-week schedule extension due to MCC gear delays (still waiting for delivery
from supplier). Project completion has now been pushed to late December of 2025.
Contractor confirming delivery of electrical gear. Currently still indicating end of May to mobilize on site
but contingent on receiving confirmation from electrical gear supplier. A formal change order to the
contract has been requested to extend the completion date as the project was originally scheduled to be
complete this spring. The new roof was installed in June of 2024. Stored materials have been relocated
from the Holzner warehouse to a storage container box located at the pump station.
Contractor submittals ongoing (approximately 85% complete with submittals). Contractor completion
date remains November of 2025 currently.
The updated construction schedule is as follows:
•
Install new doors & trim: The doors and trim work are complete.
•
Power wash building & fencing at fuel tank – will be completed when doors are installed
•
Gas line install to building – Eversource installed the line on Thursday 9/19.
•
Gas line run from regulator/ meter to building entrance – Holzner/ mechanical contractor ran
underground gas line from regulator to north side.
•
Switchgear is showing delivery late spring – once received, bulk of work will commence
•
Bypass install / contractor mobilization – mid-June
•
Electrical installation – commence once bypass system in place
•
Mechanical installation - commence once bypass system in place
•
Final site work – commence after bypass system removal
Competitive bid results for this project were received on August 10, 2023. The lowest bid received was
from Holzner Construction in the amount of $2,113,850.00 The Notice to Proceed for Holzner was
executed on January 16, 2024. A Contract Administration proposal from Wright- Pierce was executed
P a g e | 3
1/19/2024 in the amount of $55,800.00 an anticipated completion date is expected about November
2025.
3. Control Panel Retrofit
FY22 Capital Improvement Fund L.I. # 33122-55894
Original Appropriation: $30,000.00 Available Balance: $0 – line closed
Current Project Status: No change on this project in the last 30 days, this project will resume when we
move into the build phase on the SCADA project. This work is in conjunction with the SCADA system
upgrade.
Project History: To date a high definition screen was installed at the Route 85/Crystal Mall station and a
10-inch screen at Stoney Brook. All ordered parts have arrived; we anticipate beginning this project in the
next 3-4 weeks once Ridgewood Ave is complete.
Project Background: This project entails replacing the existing pump control panels, which are obsolete
and unsupported with current control technology. This work will ensue upon completion of upgrades
currently being conducted at 10 of the lift stations, which are identified within this report and are being
funded with ARPA funds.
4. Gorman-Rupp Pump Station Controls
This is an ARPA allocation project in the amount of $163,750.00. L.I. # 23531-55013
Current Project Status: No change on this project in the last 30 days.
Project History: To date Shore Road, Dock Road, Richards Grove Road, Old Barry Road, Quaker Hill
Center, Oil Mill, Oswegatchie Rd and Niantic River Road stations are complete. Ridgewood Ave station, is
the last station for this project and is nearly complete, all that remains is some work on the dry side in the
station, pending safety evaluations by our consultant.
Project Background: Utility Commission staff is performing the installation of equipment, conduits and
wiring. A scope of services change order was executed that directs the contractor to supply 18 cellular
amplifiers and associated equipment in lieu of providing broadband to 5 stations. Utility Commission staff
will be installing the amplifiers during the process of the controls upgrades. This project is ongoing.
5. Pump Station Exterior Improvements
FY22&23 Capital Improvement Fund L.I. # 33123-55895
Original Appropriations: $ 100,000.00 (50K ea. L.I.) Available Balance: $15,412.84
Current Project Status: The crew continues spring/summer cleanup at all the stations and addressing
exterior items that require work. We have identified four stations that need new roofs, and have taken
precedence over a new driveway at Cross Road.
Project History: To date under these two L.I.#s, roof replacements have occurred at Shore Road, Dock
Road, Bolles Ct, Waterford Village, Sea Side, Niantic River Rd, Mago Pt and Evergreen Ave stations. The
exterior siding was replaced at the Waterford Village and Bolles Ct stations. Siding repairs were
conducted at Stoney Brook Station. A new asphalt driveway was installed at the East Neck pump station.
6. Contract #1 Sewer Easement Access Project.
Capital Improvement Fund L.I. # 33123-55019
Original Appropriation: $250,000.00
Available Balance $147,200.00
Current Project Status: Final drawings complete addressing comments from Town Planning &
Development. Will discuss with Waterford when package will go out to bid. Project History: Final
P a g e | 4
drawings in progress to address Waterford comments. Additional drawing sent to DOT for comment
(some work will be within their jurisdiction). Drawings are 90% complete, and spec package is 100%
complete, a site walk with Wright Pierce was conducted April 9th to discuss and finalize package for
bidding. Per Wright-Pierce, drawing updates and draft specifications are in progress. A kick off call to
begin the final design package (drawing and specs) to be used for contractor bid solicitation and
construction for Phase One of the restoration project occurred on January 22, drawing updates are in
progress. Phase one will encompass the southern section of the interceptor beginning at the intersection
of Great Neck Road and Rope Ferry Road to the end of the Interceptor at Evergreen Pump Station. Phase
two which encompasses the northern section of the interceptor from Boston Post Road to Great Neck
Road requires the acquisition of additional easements to gain access to the interceptor during restoration
and for the Utility Commission staff in the future. Splitting the project into two Phases allows restoration
work to begin while easements are procured, so that once Phase one is complete easements will be in
place and Phase two can begin shortly thereafter.
Contract One Restoration Preliminary Design: W-P and WUC to have Teams meeting (tentative for
Tuesday July 16) to discuss scope for the final design and construction. Also discuss the approach for 2
new easements that may be required for interceptor access. Based on the meeting, W-P will provide a
fee proposal for the final design package (drawing and specs) to be used for contractor bid solicitation
and construction.
The request for a Special Appropriation of funds in the amount of $500,000 was approved by the Board
of Selectmen on 1/10/23. On 1/11/23 the Board of Finance acted to reduce the original request
appropriation to $250,000. On 2/6/23 the RTM approved the $250,000.00 Special appropriation. On
August 8, 2023 the Utility Commission accepted Wright–Pierce Engineers (W/P) task order proposal in
the amount of $75,200.00. Survey of the C-1 easement started October 2, 2023 and is now complete.
Wright-Pierce (W/P) submitted the Preliminary drawings on February 6, 2024. A plan review session was
conducted on February 14, 2024 at which time we identified various access alternatives.
7. Plastic Water Service Line Replacement Program
CNR Appropriation L.I. # 20531-57881
Original Appropriations: $550,000.00+$181,300.00 = $731,300.00
Available Balance: $409,001.30
An additional 100K was designated in both FY24 and FY25, a request to move from an appropriation to a
designation will take place when the currently appropriated funds are expended. The First Selectmen
included $500,000 in the General Fund Balance for FY26 to be used for Plastic Water Services, a request
to appropriate these funds will be made to enable to Utility Commission to stay one full year ahead of
DPW’s paving plan.
Current Project Status: As of 7/2/2025, B&W began their work on Old Norwich Road on June 24, 2025
and have 8 services left to complete. Our crew will begin material type identification on DPW’s FY26
paving program roads in District 3 next week, these roads include Soljer Drive, Ann Road, & Roseleah
Drive. From there we will head to the roads impacted by Eversource in Quaker Hill, as we continue our
goal to remain one full year ahead of DPW’s paving program.
Project History: Our road crew has completed their work on Albacore and Marlin. The Utility Commission
crew investigated 15 of the 20 total services between both roads and replaced 10 services, totaling 248
LF of service line replacement on these streets. A pre-construction meeting with B&W was held on May
29th, construction is anticipated to begin on June 23, 2025. Staff is working with DPW to review next few
years planned paving roads in an effort to stay ahead of DPW by a year.
P a g e | 5
The bid package for Old Norwich Road PWS replacements has been approved and is out to bid, a pre-
submittal meeting is scheduled for April 22, bids are due May 6th. Bidders are required to mobilize within
2-3 weeks of receipt of award in order to keep ahead of DPW’s paving schedule. Our crew has picked up
our mini-excavator for the season, and are preparing to begin work on Albacore the week of April 7th.
2023-2024 Project History: The Maintenance crew has completed work on Quarry Road, Goshen Road,
Leary Drive and Country Club Drive, a total of 65 services were investigated, of which 41 were identified
as plastic service lines and replaced, this amounted to 972 LF of service line replacement on these
streets. Work commenced on the Plastic Water Service Replacement Project on May 22, 2023. In Fiscal
Year 2024 the City of New London’s contract service provider, Veolia replaced 21 plastic services on
Shore Road; Waterford Utility Commission Maintenance Staff investigated a total of 425 services of
which 105 were identified as plastic services and replaced on Shore Road, Niantic River Road, Tiffany Ave,
East Brook Drive, Savi Ave, Cherry Street, Willow Street, Cedar Street, Mackenzie Road, Lark Street,
Thrush Street, Robin Street, Quail Street, Kingfisher Way, Kestrel Lane, Woodlawn Ave and Woodlawn
Court; a total of 2,584 LF of service lines were replaced. A request for an additional $181,300.00 to
replace plastic water services on Old Norwich Rd was approved by the Board of Selectman, Board of
Finance and subsequently by the RTM on August 7, 2023.
8. Wiemes & Marilyn Road Ejector Pump Replacement
CNR Appropriation L.I. # 20531-57890
$19,800.00
Current Project Status: Wright Piece is completing their draft memo which will include options for
upgrades to Gorman Rupp pre-packaged station and submersible pump/valve vault station options. The
draft memo will be complete for internal (Wright-Pierce) review July 3rd. Final draft to Waterford July
14th.
Project History: A site visit was conducted on April 2nd by Wright-Pierce, both stations were visited along
with a packaged pump station as an example of what the Utility Commission has done for building
enclosures. A signed task order was sent to Wright Pierce on March 3rd, Wright-Pierce is working with
WUC staff to gather station and force main record drawings/documentation and run time data for each
station, and a site visit to each station will be conducted within the next few weeks as they begin their
analysis. On February 2nd the RTM approved our request to appropriate the designated funds following
approval on January 15th from Board of Finance and January 7th approval from Board of Selectmen, funds
will be available 15 days thereafter, as which time the task order will be signed and the Engineering Study
can begin.
Project Background: Wiemes Ct and Marilyn Rd pump stations were designed in 1981. These stations are
known as Pneumatic Ejectors. The station itself is a steel cylinder 9' in diameter buried about 18 feet
below ground and accessed via a manway. The station houses the pots, compressors and control panel.
The stations have exceeded their design life and do not operate efficiently. An engineering study is
warranted to fully evaluate the stations structural integrity and plan for the station's replacement. In
addition, considerations for permanent stand by power should be evaluated, as portable generators have
to be mobilized in the event of need. Wright-Pierce provided a fee proposal for $19,800 to complete the
needed engineering study, a formalized task order has been requested, with the understanding the
funding must be appropriated prior to execution of the task order.
Sewer Development & Maintenance Fund Projects
9. SCADA System Upgrade Design/Build
L.I. # 24431-57766
Approved Task Order: $147,600.00
P a g e | 6
Current Project Status:
As of 7/2/2025, a workshop to transition into the build phase of the project is scheduled for July 11,
2025.
•
MQTT investigation, download of free MQTT broker.
•
Testing of MQTT broker communication.
•
Investigation of MQTT package pricing.
•
Investigation of DNP3 drivers in Ignition.
•
Update of Visio Network Drawing.
•
Email to Client on Anticipated workshop.
Project History:
Client meeting held to discuss preliminary design and finalization of the network design. Follow-up
meeting to be held on 6/6 regarding MQTT communication decisions. Network Design complete pending
changes from 6/6 meeting. A final amendment to the scope of the project was received on March 26th
after much discussion, one final addition to the scope was made to host a documentation management
portal for ease of management for all Utility Commission documentation moving forward. The total cost
for the change of scope is an additional $19,200 to their original approved task order and a timeline
extension of 6-8 weeks as a result of the verbally agreed upon scope changes. The changes to the scope
will net long term savings to the Commission over the life of the SCADA system due to the elimination of
the $2,000 monthly cost for a separate fiber internet connection which over an anticipated 7 year life of
the system equates to a cost savings of over $150,000 in internet connection fees alone, amongst other
reoccurring costs for data storage and back up.
As a result of discussions and investigations made over the last few months, an amendment to the scope
of the project will be made. This amendment was discussed at the December meeting with a
representative from Wright-Pierce and involved avoiding duplicative efforts in terms of IT
infrastructure/resources that the Town could provide the Commission, including options for fiber
connectivity, data storage, and virtualized hosts.
To date the following progress has been made on this project:
1) Project kickoff meeting held on site October 3rd. Wright-Pierce reviewed the current network
architecture and programs/ hardware.
2) Preliminary network architecture drawings in progress, coordination meeting with Waterford IT on
Dec 6h.
3) Revised preliminary network drawings based on initial/follow up discussions.
4) Verizon design meeting to review cellular network needs
5) IT meeting to discuss virtual historian and data storage.
6) Commission meeting to review modified scope per above
7) A follow up IT meeting to solidify scope changes for forthcoming amendment.
8) Conceptual SCADA hardware design 95% complete waiting on Client decision on Pump Station Wi-Fi
dot1x
9) Virtual Infrastructure Network Drawing 95% complete
10) Amendment 1 being drafted for changes as outcome of virtualization decisions.
11) HMI Development 90% Complete.
12) Currently working on putting screenshots together for client review.
Project Background: The current SCADA (Supervisory Control and Data Acquisition) system has
experienced multiple failures over the past several months, which has necessitated calling in the entire
crew to canvas the pumps stations on at least one occasion while the system was brought back online;
additionally two different software programs used to operate the system are no longer supported and
the hardware has exceeded its useful life. The Commission has entered into a design-build contract with
P a g e | 7
Wright Pierce, our on-call engineering firm, to replace the failing system. The new system platform will
be Ignition, a software system found and piloted by one of our current Maintenance Operators and
presented to the Commission over the past few years. Additionally the communication between stations
to the maintenance shop/Municipal Complex will be accomplished over a closed zero-tunnel cellular
network with radio redundancy. The Commission approved the proposal from Wright-Pierce for this
project in August of 2024, the cellular network work is outside of this proposal and is being handled by
Utility Commission staff.
10. Water and Wastewater Standards and Specifications Update
L.I. # 24431-52121
Approved Task Order: $36,800.00
Current Project Status: No updates on this project at this time. Waterford sent the draft standards and
specs to New London for their initial comments on May 13, 2025.
Project History: Wright Pierce Update as of 4/3/25: Water specifications and standard details draft
submitted for review by Waterford staff. WUC staff is currently reviewing.
Project Background: The current Water and Wastewater Standard and Specifications the Utility
Commission uses are significantly outdated and require updating. This project is being cost-shared with
the City of New London.
Utility Commission Operational Projects
•
All wastewater collection system components and equipment are operational with the exception of
pump one at Harvey Ave and the generator at Oil Mill Road.
•
Harvey Ave Update: Awaiting estimate for pump repair.
•
Oil Mill Generator: Awaiting decision from insurance company regarding claim on generator
replacement and rental unit. We received a quote for its replacement from our Cummins rep
in the amount of $110,389.00 and a lead time of 20-25 weeks. The lowest generator rental
quote came in at $4950/month from Generators On Demand.
•
Asset Management update:
•
Assistant Director to provide an update.
•
Municipal Waterworks Meetings: a meeting is scheduled for July 17th.
•
Municipal Wastewater Flow Metering verification was performed by an independent vendor, the Utility
Commission and the City of New London will engage Flow Assessment Services to manage the inter-
municipal flow meters with full transparency and ensuring both municipalities have real time access to
the data at all times moving forward. A quote was received from Flow Assessments to calibrate the
meters, 5 total, twice a year for $6,500 annually. We will share the costs with New London for this
proposal.
•
OSHA Update –
•
An informal conference was held with OSHA on June 10th which resulted in a reduction of
penalties from $7,660 to $4,550, a copy of the Informal Settlement Agreement will be
provided to the Commissioner’s as Correspondence.
•
All non-confined space related violations have been abated as of June 10th
•
Our safety consultant was engaged on May 1st to evaluate all confined spaces and train our
staff on proper Confined Space Entry and Rescue specific to our operation, as well as develop
a complete Safety Program for our operation that meets OSHA requirements. To date our staff
have been trained as of June 24th and nearly all of our confined spaces have been evaluated
and will return on July 10th to complete the four outstanding stations. We will receive reports
on all potential confined spaces evaluated to include a determination as to whether or not
P a g e | 8
they are a confined space, if they are a permit entry required space, and recommendations to
mitigate and safety hazards identified. We have received a comprehensive draft Safety
Program and are in the midst of the review and editing process to finalize the plan before
implementation with the staff.
Respectfully Submitted,
Jill N. Stevens
Director of Utilities