WATERFORD UTILITY COMMISSION
DATE:
November 12, 2025
PLACE:
1000 Hartford Turnpike
PRESIDING:
Chairman Ken Kirkman
MEMBERS PRESENT:
Jerry Porter and Ray Valentini
ABSENT MEMBERS:
Ryan Boyle
ALSO PRESENT: Staff: Jill Stevens, Director of Utilities
Amy Windle, Office Coordinator/Recording Secretary
Chairman Kirkman called the meeting to order at 6:01 pm
Moment of Silence for Thomas Dembek
CITIZEN SESSION-
Owner of 37 Boston Post Road came in to request an adjustment on his sewer bill from a large leak in his
hot water heater. The Commission requested documentation in order to grant an adjustment using a
five-year average.
SECRETARY’S REPORT
MOTION
Made by Mr. Valentini to approve the Minutes of October 14, 2025, Mr. Porter
seconded.
VOTE
The motion passed unanimously.
BILLING ADJUSTMENTS
The Commission reviewed the October adjustments. The adjustment report will be kept in the
office for review.
EXPENDITURES
MOTION
Made by Mr. Valentini to approve the October 2025 bill list, Mr. Porter
seconded.
VOTE
The motion passed unanimously.
OLD BUSINESS
•
Financial Report
The financials for September were reviewed.
Waterford Utility Commission
November 12, 2025
2 | P a g e
•
Collection’s Report
The report was reviewed.
•
Director’s Report
Ms. Stevens reviewed her report that provides updated information on all Utility
Commission Capital and Operational projects currently funded. A copy of the Director’s
Report will be attached to the minutes when posted.
M. Stevens reviewed the Asset Management report.
NEW BUSINESS
WATER
City of New London/Veolia Report.
The Commission reviewed the report.
Water Agreement Working Group Update
No updates at this time.
CORRESPONDENCE
PLANS REVIEW –
No plans
PERSONNEL
Sewer Tech I position is still vacant due to new hire accepting another higher paying position.
OTHER
ADJOURNMENT
With no further business before the Commission, the meeting adjourned at 6:46 p.m.
MOTION
Made by Mr. Porter to adjourn, Mr. Valentini seconded.
VOTE
The motion passed unanimously.
Respectfully submitted,
Amy Windle
Recording Secretary
P a g e | 1
Waterford Utility Commission
Director’s Report
November 12, 2025
This report summarizes the Commission’s ongoing projects and operational activities as of 11/4/25
Current Capital and Capital Non-Recurring Funded Projects
1. Inflow and Infiltration Mitigation and Control
FY 19 Capital Non-Recurring Expenditure Fund L.I. #20531-57685
Original Appropriation: $388,303.00 Available Balance: $235,865.56
This is an ongoing project to identify sources of Inflow and Infiltration within the Richards Grove Sewer
Basin.
Current Project Status: No change to this project this month. Waterford crew continues to install
manhole dishes within the wastewater basin as time permits, flow monitoring will be conducted again
after all manhole dishes have been installed to determine if surface runoff is the majority source of the
inflow.
Richards Grove SSES – an updated memo was submitted including additional CCTV footage review (2025
CCTV video) and further analysis with the recent flow metering data and water usage data and was
included in your packets at the August meeting.
Project Background: The Richards Grove Road Wastewater Basin Inflow & Infiltration (I&I) evaluation
being conducted by Wright-Pierce Engineers for the amount of $27,500.00. This project consists of
conducting I&I evaluations and a Sewer System Evaluation Study (SSES). This drainage area has been
identified as one of the larger contributors of I&I to our Collection System. This area possesses
approximately 5 miles of 8-inch diameter gravity sewer piping and serves primarily residential users. The
current flows received and conveyed by the Richards Grove Pump Station are greater than the capacity of
the pump station, triggering the potential need for a capacity upgrade if the I&I sources cannot be
identified and mitigated. The I&I mitigation and control program is an ongoing project. Our staff routinely
conducts pipeline and manhole assessments with the use of our CCTV and Jet Rodding apparatus.
Deficiencies are located, graded and catalogued based upon severity. Corrective repairs are typically
conducted during springtime utilizing robotic trenchless technology.
2. Old Norwich Road Wastewater Pump Station Rehabilitation
There are two CNR designations totaling $1,299,369 in L.I. # 20531-57816.
Available CNR Balance: $31,318.46 (including encumbrances)
In addition, available ARPA funds have been increased to $1,341,316 per finance as of June 4, 2025.
Original ARPA funds available were in the amount of $1,020,041.
P a g e | 2
Current Project Status: The station is currently on by-pass and construction continues. The transformer
work will be done 11/12 or 11/14 (rain date) – we are meeting with Wright Pierce to discuss the status of
several change orders on 11/17/25.
Project Background: This project entails an upgrades needed to replace aging equipment at the Old
Norwich Road pump station. The upgrades include the replacement of the three sewage pumps and
associated piping and valves and the installation of a new bypass pumping connection. Comprehensive
upgrades will also be performed for the electrical systems including replacement of conduit and wiring
and the electrical distribution and pump control systems. The ventilation system will also be
replaced. Painting and minor architectural improvements will be performed to replace the exterior
doors, louvers, trim and roof. Competitive bid results for this project were received on August 10, 2023.
The lowest bid received was from Holzner Construction in the amount of $2,113,850.00 The Notice to
Proceed for Holzner was executed on January 16, 2024. A Contract Administration proposal from Wright-
Pierce was executed 1/19/2024 in the amount of $55,800.00 an anticipated completion date was
expected about November 2025, however the contractor has provided an updated final completion date
of 2/11/2026.
3. Control Panel Retrofit
FY22 Capital Improvement Fund L.I. # 33122-55894
Original Appropriation: $30,000.00 Available Balance: $0 – line closed
Current Project Status: No change on this project in the last 30 days, this project will resume when we
move into the build phase on the SCADA project.
Project Background: This project entails replacing the existing pump control panels, which are obsolete
and unsupported with current control technology. This work will ensue upon completion of upgrades
currently being conducted at 10 of the lift stations, which are identified within this report and are being
funded with ARPA funds.
4. Gorman-Rupp Pump Station Controls
This is an ARPA allocation project in the amount of $163,750.00. L.I. # 23531-55013
Current Project Status: Work has resumed at Ridgewood Ave.
Project History: To date Shore Road, Dock Road, Richards Grove Road, Old Barry Road, Quaker Hill
Center, Oil Mill, Oswegatchie Rd and Niantic River Road stations are complete. Ridgewood Ave station, is
the last station for this project and is nearly complete, all that remains is some work on the dry side in the
station, this work will resume now that the safety consultant has completed his evaluations and
additional gear has been procured.
Project Background: Utility Commission staff is performing the installation of equipment, conduits and
wiring. A scope of services change order was executed that directs the contractor to supply 18 cellular
amplifiers and associated equipment in lieu of providing broadband to 5 stations. Utility Commission staff
will be installing the amplifiers during the process of the controls upgrades. This project is ongoing.
5. Pump Station Exterior Improvements
FY22&23 Capital Improvement Fund L.I. # 33123-55895
Original Appropriations: $ 100,000.00 (50K ea. L.I.) Available Balance: $16,719.48
Current Project Status: The crew continues regular exterior maintenance work at all the stations
including landscape upkeep. We have identified four stations that need new roofs, and have taken
precedence over a new driveway at Cross Road. Due to staffing shortages this project has been delayed
until next year.
Project History: To date under these two L.I.#s, roof replacements have occurred at Shore Road, Dock
Road, Bolles Ct, Waterford Village, Sea Side, Niantic River Rd, Mago Pt and Evergreen Ave stations. The
P a g e | 3
exterior siding was replaced at the Waterford Village and Bolles Ct stations. Siding repairs were
conducted at Stoney Brook Station. A new asphalt driveway was installed at the East Neck pump station.
6. Contract #1 Sewer Easement Access Project
Capital Improvement Fund L.I. # 33123-55019 & FY26 CNR L.I. # 20531-57894
Original Appropriation: $250,000.00 & Additional Designation: FY26 CNR $200,000
Available Balance $341,580.88
Current Project Status: The contract was awarded to Advanced Resources, a pre-construction meeting is
scheduled for 11/12 at 10am. Construction is anticipated to begin this month.
Project Background: Contract #1 was the Town's very first sewer construction project, which began in
1970. This project entailed the installation of approximately 13,000 linier feet of sewer main. A Special
Appropriation in the amount of $250,000 for engineering services was appropriated for the Contract #1
Sewer Main Access project in 2023. Survey work to identify the Contract #1 easement area, manholes,
intersecting property lines, and other utilities within the easement area commenced in October of 2023
and was completed in the spring of 2024. The final design package (drawings and specifications) to be
used for contractor bid solicitation and construction for Phase One of the restoration project was
approved by the Utility Commission at the November 2024 meeting. Phase one encompasses the
southern section of the interceptor beginning at the intersection of Great Neck Road and Rope Ferry
Road to the end of the interceptor at Evergreen Avenue Pump Station. Phase two which encompasses
the northern section of the interceptor from Boston Post Road to Great Neck Road requires the
acquisition of additional easements to gain access to the interceptor during restoration and for the Utility
Commission staff in the future. Splitting the project into two Phases allows restoration work to begin
while easements are procured, so that once Phase one is complete easements will be in place and Phase
two can begin shortly thereafter.
7. Plastic Water Service Line Replacement Program
CNR Appropriation L.I. # 20531-57881
Original Appropriations: $550,000.00+$181,300.00 = $731,300.00
Additional Designations: $200,000 total in FY24 & FY25, & $500,000 in FY26 GFB
Available Balance: $784748.62
Current Project Status: In FY26 the DPW’s updated paving plan has identified several roads scheduled to
be repaved, within these roads lie approximately 376 water services, of those approximately 165 may
need to be replaced, as the material type is unconfirmed. The WUC maintenance crew completed
material type identification on DPW’s FY26 paving program roads in District 3. We are working on the
roads impacted by Eversource in Quaker Hill to determine material types and plan for replacements, as
we continue our goal to remain one full year ahead of DPW’s paving program.
Project Background: There are approximately 7900 water services in Town, many of which are plastic and
have exceeded their useful life resulting in unaccounted for water loss and degradation to the Town
roads. The goal of this program is to replace the aging plastic water services with copper line prior to
DPW paving the roads. Since the start of this cooperative project with DPW 806 water service lines have
been investigated, of those 229 water service lines were found to be plastic and replaced totaling 5,218
linear feet. Service line replacement costs are on average $4100 each depending upon the service line
length and location, typically we are finding about 30 percent of the unconfirmed service material types
are plastic and require replacement.
8. Wiemes & Marilyn Road Ejector Pump Replacement
CNR Appropriation L.I. # 20531-57890
Original Appropriation: $19,800.00
Available Balance: $0 – line closed
P a g e | 4
Current Project Status: The Wright-Pierce memo has been provided to one of our pump
suppliers/vendors for alternate solutions to cut costs; provided we have some detention time, standby
power is not needed at these stations which should significantly cut replacement costs.
Project Background: Wiemes Ct and Marilyn Rd pump stations were designed in 1981. These stations are
known as Pneumatic Ejectors. The station itself is a steel cylinder 9' in diameter buried about 18 feet
below ground and accessed via a manway. The station houses the pots, compressors and control panel.
The stations have exceeded their design life and do not operate efficiently. An engineering study was
warranted to fully evaluate the stations structural integrity and plan for the station's replacement. In
addition, considerations for permanent stand by power were be evaluated, as portable generators have
to be mobilized in the event of need. Wright-Pierce provided a fee proposal for $19,800 to complete the
needed engineering study, a formalized task order was been requested and executed earlier this year.
9. Bartlett Corners Booster Station Decommissioning
CNR Designation L.I. #20531-57896
Original Appropriation: $166,950
Current Project Status: Staff is reviewing Haley Ward’s task order to begin this project.
Project Background: In 2006, the Town constructed water system improvements that enhanced water
pressures and fire flows to the Quaker Hill area of Waterford. Included in this project were a new 2500
gpm capacity water booster pumping station near the intersection of Old Colchester and Old Norwich
Roads, and a 1.5 million gallon pre-cast, pre-stressed concrete water storage tank constructed on Rogers
Hill. From 1977 up to 2006, the Bartlett Corners Hydro-pneumatic Station served a small high service area
on a hill in the northeast corner of Waterford consisting of approximately 20 residential customers on
Lathrop Road, Lower Bartlett Road, Upper Bartlett Road, Pepperidge Road and South Bartlett Road. Once
the new Quaker Hill water system improvements were activated in 2006, the Bartlett Corners Station was
inactivated however not fully decommissioned. In 2009 a decommissioning report was prepared which
identified costs of $105,000 to properly decommission the station. This project has been identified within
previous CIPs. Utilizing the Engineering News Record’s Construction Costs Index inflation factor of 1.59
from 11/2009 to 11/2024, the current decommissioning costs estimate is $166,950.
10. Water Tank Asset Management Program
CNR Appropriation L.I. # 20531-57895
Original Designation: $46,222
Current Project Status: The contract has been signed and provided to USG Water to enroll the tank in the
Asset Management program. The first annual tank inspection will be scheduled for the spring of 2026.
Project Background: The Town of Waterford owns three water storage tanks, the 750,000 gallon Fargo
Tank, the 300,000 gallon Vauxhall tank and the 1.25 Million gallon Rogers Hill tank. In 2024 the Fargo
Road Tank refurbishment project was completed; prior to this renovation, the Fargo Road water tank had
its original coat of paint, which had far exceeded its useful life expectancy by approximately 10 years. This
work was necessary to preserve the Town’s significant investment in its infrastructure and to extend the
life of its asset. A Water Tank Management Program for these valuable assets would preserve the
significant investment the Town has made in water storage tanks by guaranteeing routine inspections
and maintenance of the water storage tanks does not fall behind, thus improving the reliability of the
system. A sustainable water tank management solution also makes budgeting easier as initial repair costs
can be spread out over a few years if necessary and all future interior and exterior renovation costs are
included. Our intent is to initiate a funding schedule that would enroll the three water storage tanks in a
Tank Asset Management program progressively, beginning with Fargo Road in FY26, this tank will not
require any Upfront Renovation costs to enroll in the program, only annual Maintenance plan costs.
P a g e | 5
Sewer Development & Maintenance Fund Projects
11. SCADA System Upgrade Design/Build
L.I. # 24431-57766
Approved Task Order: $147,600.00 + $19,200 change order in March: $166,800
Current Project Status:
Update to be provided by W-P prior to Commission meeting.
Project Background: The current SCADA (Supervisory Control and Data Acquisition) system has
experienced multiple failures over the past several months, which has necessitated calling in the entire
crew to canvas the pumps stations on at least one occasion while the system was brought back online;
additionally two different software programs used to operate the system are no longer supported and
the hardware has exceeded its useful life. The Commission has entered into a design-build contract with
Wright Pierce, our on-call engineering firm, to replace the failing system. The new system platform will be
Ignition, a software system found and piloted by one of our current Maintenance Operators and
presented to the Commission over the past few years. Additionally the communication between stations
to the maintenance shop/Municipal Complex will be accomplished over a closed zero-tunnel cellular
network with radio redundancy. The Commission approved the proposal from Wright-Pierce for this
project in August of 2024, the cellular network work is outside of this proposal and is being handled by
Utility Commission staff. An amendment was discussed at the December meeting with a representative
from Wright-Pierce and involved avoiding duplicative efforts in terms of IT infrastructure/resources that
the Town could provide the Commission, including options for fiber connectivity, data storage, and
virtualized hosts. A final amendment to the scope of the project was received on March 26, 2025 after
much discussion, an addition to the scope was made to host a documentation management portal for
ease of management for all Utility Commission documentation moving forward. The total cost for the
change of scope is an additional $19,200 to their original approved task order and a timeline extension of
6-8 weeks as a result of the agreed upon scope changes. The changes to the scope will net long term
savings to the Commission over the life of the SCADA system due to the elimination of the $2,000
monthly cost for a separate fiber internet connection which over an anticipated 7 year life of the system
equates to a cost savings of over $150,000 in internet connection fees alone, amongst other reoccurring
costs for data storage and back up.
12. Water and Wastewater Standards and Specifications Update
L.I. # 24431-52121
Approved Task Order: $36,800.00
Current Project Status: No updates on this project at this time. Waterford sent the draft standards and
specs to New London for their initial comments on May 13, 2025. Due to staffing shortages and some
reorganization in New London this cooperative project is on hold.
Project Background: The current Water and Wastewater Standard and Specifications the Utility
Commission uses are significantly outdated and require updating. This project is being cost-shared with
the City of New London.
Utility Commission Operational Projects
•
All wastewater collection system components and equipment are operational with the exception of the
following components:
•
Harvey Ave Update: pump repair is complete delivery will be coordinated with retrieval of pump four
at Evergreen.
•
Evergreen Pump Four: The pump has a bad bearing and needs to be repaired, pump one has been
put back online so that pump four can be pulled and repaired. When pump four is reinstalled, pump
one will go out for inspection and repaired if needed.
•
Evergreen Pump One: The pump is making a ticking noise and is still has a percentage of the warranty
left, WUC staff removed the suction elbow and verified that there were no foreign objects lodged in
P a g e | 6
the pump. The pump will be pulled when the Harvey Ave pump is delivered so it can be inspected
and repaired if needed after pump four is pulled, repaired and reinstalled.
•
Oil Mill Generator: The station is operational with a rental standby generator in place, the signed
contract was sent to our Cummins rep on August 13th to initiate the replacement of the generator.
Lead time is 20-25 weeks, no new updates at this time as we continue to wait for delivery.
•
Asset Management update: Assistant Director to provide an update.
•
Municipal Waterworks Meetings: a meeting is scheduled for November 20th
•
Flow metering – we are working on setting up a meeting with EST to provide maintenance contract
services for our existing meters.
Respectfully Submitted,
Jill N. Stevens
Director of Utilities