Utility Commission - Minutes - 01/13/2026

agenda center minutes

Board/CommissionUtility Commission
Meeting DateJanuary 13, 2026
Pages8
File Size0.4 MB
OCR Status Searchable (OCR processed)
Source URLOriginal
Download PDF

Document Preview

Full Text (OCR Extracted)
WATERFORD UTILITY COMMISSION 
 
 
 
 
 
 
DATE:  
 
January 13, 2026 
 
PLACE:  
 
1000 Hartford Turnpike  
 
PRESIDING: 
 
Chairman Ken Kirkman 
 
MEMBERS PRESENT: 
Jerry Porter, Beth Sabilia, Ryan Boyle and Ray Valentini 
 
ALSO PRESENT:   
J. Robert Tuneski, Board of Finance Liaison  
 
 
             Attorney Nicholas Kepple, Town Counsel 
                 
                Staff: Jill Stevens, Director of Utilities  
 
 
            Shawn Matthews, Assistant Director of Utilities 
            Amy Windle, Office Coordinator/Recording Secretary 
 
Chairman Kirkman called the meeting to order at 6:00 pm 
 
Chairman Kirkman welcomed the new member of the Commission, Beth Sabilia. 
 
 
CITIZEN SESSION-             
None 
 
SECRETARY’S REPORT 
 
MOTION 
Made by Mr. Boyle to approve the Minutes of December 9, 2025, Mr. Valentini 
seconded. 
 
VOTE 
 
 The motion passed.  4-Yes  1-Abstained 
 
  BILLING ADJUSTMENTS 
 
The Commission reviewed the December adjustments. The adjustment report will be kept in the 
office for review.  
 
 
EXPENDITURES 
 
MOTION 
Made by Mr. Porter to approve the December 2025 bill list, Mr. Valentini 
seconded. 
 
VOTE 
 
The motion passed unanimously. 
 

Waterford Utility Commission 
January 13, 2026 
2 | P a g e  
 
OLD BUSINESS 
• 
Financial Report 
The financials for November were reviewed.  
 
• 
Collection’s Report 
Attorney Kepple reported that his staff is on track to collect the amount that was 
collected last year. 
 
• 
Director’s Report 
Ms. Stevens reviewed her report that provides updated information on all Utility 
Commission Capital and Operational projects currently funded. A copy of the Director’s 
Report will be attached to the minutes when posted. 
 
Mr. Matthews reviewed the Asset Management report. 
 
NEW BUSINESS 
EST Continuous Flow Monitoring Services proposal 
 
Ms. Stevens went over the proposal and the need for the services. 
 
 
MOTION 
made by Mr. Valentini to go with the quote from EST up to the amount of 
 $50, 000, seconded by Mr. Porter. 
 
VOTE 
 
 The motion passed unanimously. 
 
 
WATER  
City of New London/Veolia Report. 
The Commission reviewed the report.  Ms. Stevens reported that New London has notified her that Lake 
Konomoc is entering a drought warning status. 
 
Water Agreement Working Group Update 
Attorney Kepple gave an update on this working group.   
MOTION 
made by Ms. Sabilia to disband the Water Agreement Working Group and leave 
the exploration of Waterford’s future water sources to the Utility Commission, 
seconded by Mr. Boyle. 
VOTED 
The motion passed unanimously. 
CORRESPONDENCE 
 
• 
Compliant received from resident by phone and documented in an email by staff was 
reviewed regarding the Sewer Rebate program. 
• 
Minutes from East Lyme and Old Lyme 

Waterford Utility Commission 
January 13, 2026 
3 | P a g e  
 
• 
Public Comment statement that was submitted to the Board of Selectmen from Mr. 
Schacht regarding water planning agenda item at the December 15, 2025 meeting. 
• 
Fargo Water Tank Annual Inspection Report 
 
PLANS REVIEW –  
No plans 
 
PERSONNEL 
Sewer Tech I position is still vacant.  There is one application that needs to be reviewed. 
  
OTHER 
 
ADJOURNMENT 
 
With no further business before the Commission, the meeting adjourned at 7:34 p.m. 
 
 
 
MOTION 
Made by Mr. Boyle to adjourn, Mr. Valentini seconded. 
 
 
 
VOTE 
 
The motion passed unanimously. 
 
 
 
Respectfully submitted, 
 
 
Amy Windle 
Recording Secretary 

P a g e  | 1 
 
 
 
 
 
Waterford Utility Commission 
Director’s Report 
January 13, 2026 
             This report summarizes the Commission’s ongoing projects and operational activities as of 1/8/26 
Current Capital and Capital Non-Recurring Funded Projects 
1. Inflow and Infiltration Mitigation and Control 
FY 19 Capital Non-Recurring Expenditure Fund L.I. #20531-57685  
 
Original Appropriation: $388,303.00       Available Balance: $235,865.56 
This is an ongoing project to identify sources of Inflow and Infiltration within the Richards Grove Sewer 
Basin.  
Current Project Status: No change to this project this month. Waterford crew continues to install 
manhole dishes within the wastewater basin as time permits, flow monitoring will be conducted again 
after all manhole dishes have been installed to determine if surface runoff is the majority source of the 
inflow. 
Richards Grove SSES – Wright Pierce will assist with recommendations for future flow monitoring in the 
spring of 2026. 
Project Background: The Richards Grove Road Wastewater Basin Inflow & Infiltration (I&I) evaluation 
being conducted by Wright-Pierce Engineers for $27,500.00. This project consists of conducting I&I 
evaluations and a Sewer System Evaluation Study (SSES). This drainage area has been identified as one of 
the larger contributors of I&I to our Collection System. This area possesses approximately 5 miles of 8-
inch diameter gravity sewer piping and serves primarily residential users. The current flows received and 
conveyed by the Richards Grove Pump Station are greater than the capacity of the pump station, 
triggering the potential need for a capacity upgrade if the I&I sources cannot be identified and mitigated. 
The I&I mitigation and control program is an ongoing project. Our staff routinely conducts pipeline and 
manhole assessments with the use of our CCTV and Jet Rodding apparatus. Deficiencies are located, 
graded and catalogued based upon severity. Corrective repairs are typically conducted during springtime 
utilizing robotic trenchless technology. 
 
2. Old Norwich Road Wastewater Pump Station Rehabilitation 
There are two CNR designations totaling $1,299,369 in L.I. # 20531-57816.   
In addition, available ARPA funds have been increased to $1,341,316 per finance as of June 4, 2025. 
Original ARPA funds available were in the amount of $1,020,041. 
Current Project Status: The station is currently on by-pass and construction continues. Construction in 
progress.  Contractor installing new switchgear over the next several weeks. Pumps, piping and HVAC 

P a g e  | 2 
 
system mostly complete.  We do not have a formal update from the contractor, however it appears that 
the project completion date will slide into March at this point. 
   
Project Background: This project entails an upgrades needed to replace aging equipment at the Old 
Norwich Road pump station. The upgrades include the replacement of the three sewage pumps and 
associated piping and valves and the installation of a new bypass pumping connection.  Comprehensive 
upgrades will also be performed for the electrical systems including replacement of conduit and wiring 
and the electrical distribution and pump control systems.  The ventilation system will also be 
replaced.  Painting and minor architectural improvements will be performed to replace the exterior 
doors, louvers, trim and roof.  Competitive bid results for this project were received on August 10, 2023. 
The lowest bid received was from Holzner Construction in the amount of $2,113,850.00 The Notice to 
Proceed for Holzner was executed on January 16, 2024. A Contract Administration proposal from Wright- 
Pierce was executed 1/19/2024 in the amount of $55,800.00 an anticipated completion date was 
expected about November 2025, however the contractor has provided an updated final completion date 
of 2/11/2026. 
3. Control Panel Retrofit 
FY22 Capital Improvement Fund L.I. # 33122-55894 
Original Appropriation: $30,000.00       Available Balance: $0 – line closed 
Current Project Status: No change on this project in the last 30 days, this project will resume when we 
move into the build phase on the SCADA project at the end of January/beginning of February.  
Project Background: This project entails replacing the existing pump control panels, which are obsolete 
and unsupported with current control technology. This work will ensue upon completion of upgrades 
currently being conducted at 10 of the lift stations, which are identified within this report and are being 
funded with ARPA funds. 
 
4. Gorman-Rupp Pump Station Controls 
This is an ARPA allocation project in the amount of $163,750.00. L.I. # 23531-55013 
Current Project Status: Some progress has been made at Ridgewood Ave, after replacing the pumps in 
early December, we are installing the remaining screens and completing the electrical work in 
conjunction with the SCADA project. 
Project History: To date Shore Road, Dock Road, Richards Grove Road, Old Barry Road, Quaker Hill 
Center, Oil Mill, Oswegatchie Rd and Niantic River Road stations are complete. Ridgewood Ave station, is 
the last station for this project and is nearly complete, all that remains is some work on the dry side in the 
station, this work will resume now that the safety consultant has completed his evaluations and 
additional gear has been procured.  
Project Background: Utility Commission staff is performing the installation of equipment, conduits and 
wiring. A scope of services change order was executed that directs the contractor to supply 18 cellular 
amplifiers and associated equipment in lieu of providing broadband to 5 stations. Utility Commission staff 
will be installing the amplifiers during the process of the controls upgrades. This project is ongoing. 
 
5. Pump Station Exterior Improvements 
FY22&23 Capital Improvement Fund L.I. # 33123-55895 
Original Appropriations: $ 100,000.00 (50K ea. L.I.)      Available Balance: $16,719.48 
Current Project Status: The crew continues regular exterior maintenance work at all the stations 
including landscape upkeep. We have identified four stations that need new roofs, and have taken 
precedence over a new driveway at Cross Road. Due to staffing shortages this project has been delayed 
until the summer of 2026. 

P a g e  | 3 
 
Project History: To date under these two L.I.#s, roof replacements have occurred at Shore Road, Dock 
Road, Bolles Ct, Waterford Village, Sea Side, Niantic River Rd, Mago Pt and Evergreen Ave stations. The 
exterior siding was replaced at the Waterford Village and Bolles Ct stations. Siding repairs were 
conducted at Stoney Brook Station. A new asphalt driveway was installed at the East Neck pump station.  
 
6. Contract #1 Sewer Easement Access Project 
Capital Improvement Fund L.I. # 33123-55019 & FY26 CNR L.I. # 20531-57894  
Original Appropriation: $250,000.00 & Additional Designation: FY26 CNR $200,000  
Available Balance $341,580.88 
Current Project Status: Advanced Resources began construction on December 10, 2025, light clearing has 
started along Great Neck Road near the intersection with Rope Ferry Road and around the high school.  
Project Background: Contract #1 was the Town's very first sewer construction project, which began in 
1970. This project entailed the installation of approximately 13,000 linier feet of sewer main.  A Special 
Appropriation in the amount of $250,000 for engineering services was appropriated for the Contract #1 
Sewer Main Access project in 2023. Survey work to identify the Contract #1 easement area, manholes, 
intersecting property lines, and other utilities within the easement area commenced in October of 2023 
and was completed in the spring of 2024. The final design package (drawings and specifications) to be 
used for contractor bid solicitation and construction for Phase One of the restoration project was 
approved by the Utility Commission at the November 2024 meeting. Phase one encompasses the 
southern section of the interceptor beginning at the intersection of Great Neck Road and Rope Ferry 
Road to the end of the interceptor at Evergreen Avenue Pump Station. Phase two which encompasses 
the northern section of the interceptor from Boston Post Road to Great Neck Road requires the 
acquisition of additional easements to gain access to the interceptor during restoration and for the Utility 
Commission staff in the future. Splitting the project into two Phases allows restoration work to begin 
while easements are procured, so that once Phase one is complete easements will be in place and Phase 
two can begin shortly thereafter. 
 
7. Plastic Water Service Line Replacement Program 
CNR Appropriation L.I. # 20531-57881       
Original Appropriations: $550,000.00 + $181,300.00 = $731,300.00  
Additional Designations: $200,000 total in FY24 & FY25 ($100K each year), & $500,000 in FY26 GFB 
Available Balance: $784,748.62 
Current Project Status:  In FY26 the DPW’s updated paving plan has identified several roads scheduled to 
be repaved, within these roads lie approximately 376 water services, of those approximately 165 may 
need to be replaced, as the material type is unconfirmed. The WUC maintenance crew completed 
material type identification on DPW’s FY26 paving program roads in District 3. We will be working on the 
roads impacted by Eversource in Quaker Hill to determine material types and plan for replacements 
beginning in early 2026, as we continue our goal to remain one full year ahead of DPW’s paving program.  
Project Background: There are approximately 7900 water services in Town, many of which are plastic and 
have exceeded their useful life resulting in unaccounted for water loss and degradation to the Town 
roads. The goal of this program is to replace the aging plastic water services with copper line prior to 
DPW paving the roads. Since the start of this cooperative project with DPW 806 water service lines have 
been investigated, of those 229 water service lines were found to be plastic and replaced totaling 5,218 
linear feet. Service line replacement costs are on average $4100 each depending upon the service line 
length and location, typically we are finding about 30 percent of the unconfirmed service material types 
are plastic and require replacement. 
 
 

P a g e  | 4 
 
8. Bartlett Corners Booster Station Decommissioning 
CNR Designation L.I. #20531-57896 
Original Appropriation: $166,950 
Current Project Status: Staff is reviewing Haley Ward’s task order to begin this project. 
Project Background: In 2006, the Town constructed water system improvements that enhanced water 
pressures and fire flows to the Quaker Hill area of Waterford. Included in this project were a new 2500 
gpm capacity water booster pumping station near the intersection of Old Colchester and Old Norwich 
Roads, and a 1.5 million gallon pre-cast, pre-stressed concrete water storage tank constructed on Rogers 
Hill. From 1977 up to 2006, the Bartlett Corners Hydro-pneumatic Station served a small high service area 
on a hill in the northeast corner of Waterford consisting of approximately 20 residential customers on 
Lathrop Road, Lower Bartlett Road, Upper Bartlett Road, Pepperidge Road and South Bartlett Road.  Once 
the new Quaker Hill water system improvements were activated in 2006, the Bartlett Corners Station was 
inactivated however not fully decommissioned. In 2009 a decommissioning report was prepared which 
identified costs of $105,000 to properly decommission the station. This project has been identified within 
previous CIPs. Utilizing the Engineering News Record’s Construction Costs Index inflation factor of 1.59 
from 11/2009 to 11/2024, the current decommissioning costs estimate is $166,950.  
9. Water Tank Asset Management Program 
CNR Appropriation L.I. # 20531-57895 
Original Designation: $46,222 
Current Project Status: The contract was signed and provided to USG Water to enroll the tank in the 
Asset Management program. The first visual tank inspection of the tank occurred Monday 12/1/2025. 
Project Background: The Town of Waterford owns three water storage tanks, the 750,000 gallon Fargo 
Tank, the 300,000 gallon Vauxhall tank and the 1.25 Million gallon Rogers Hill tank. In 2024 the Fargo 
Road Tank refurbishment project was completed; prior to this renovation, the Fargo Road water tank had 
its original coat of paint, which had far exceeded its useful life expectancy by approximately 10 years. This 
work was necessary to preserve the Town’s significant investment in its infrastructure and to extend the 
life of its asset. A Water Tank Management Program for these valuable assets would preserve the 
significant investment the Town has made in water storage tanks by guaranteeing routine inspections 
and maintenance of the water storage tanks does not fall behind, thus improving the reliability of the 
system. A sustainable water tank management solution also makes budgeting easier as initial repair costs 
can be spread out over a few years if necessary and all future interior and exterior renovation costs are 
included. Our intent is to initiate a funding schedule that would enroll the three water storage tanks in a 
Tank Asset Management program progressively, beginning with Fargo Road in FY26, this tank will not 
require any Upfront Renovation costs to enroll in the program, only annual Maintenance plan costs.  
Sewer Development & Maintenance Fund Projects 
10. SCADA System Upgrade Design/Build 
L.I. # 24431-57766  
Approved Task Order: $147,600.00 + $19,200 change order in March: $166,800 
Current Project Status:  
Installation of the Utility Commission sub-panel in the Municipal Complex electrical / data closet was 
completed December 18th, WUC staff will be deploying the zero tunnel network and edge routers needed 
to enable station communication the week of 1/19 and 1/26, Wright Pierce will be on site the week 
1/26/26 to deploy the WUC server, and the week of Feb 2nd to install and configure all final software. We 
anticipate a full cut over to the Ignition platform and project completion by Feb 27th. 
Project Background: The current SCADA (Supervisory Control and Data Acquisition) system has 
experienced multiple failures over the past several months, which has necessitated calling in the entire 
crew to canvas the pumps stations on at least one occasion while the system was brought back online; 
additionally two different software programs used to operate the system are no longer supported and 
the hardware has exceeded its useful life. The Commission has entered into a design-build contract with 

P a g e  | 5 
 
Wright Pierce, our on-call engineering firm, to replace the failing system. The new system platform will be 
Ignition, a software system found and piloted by one of our current Maintenance Operators and 
presented to the Commission over the past few years. Additionally the communication between stations 
to the maintenance shop/Municipal Complex will be accomplished over a closed zero-tunnel cellular 
network with radio redundancy. The Commission approved the proposal from Wright-Pierce for this 
project in August of 2024, the cellular network work is outside of this proposal and is being handled by 
Utility Commission staff. An amendment was discussed at the December meeting with a representative 
from Wright-Pierce and involved avoiding duplicative efforts in terms of IT infrastructure/resources that 
the Town could provide the Commission, including options for fiber connectivity, data storage, and 
virtualized hosts. A final amendment to the scope of the project was received on March 26, 2025 after 
much discussion, an addition to the scope was made to host a documentation management portal for 
ease of management for all Utility Commission documentation moving forward. The total cost for the 
change of scope is an additional $19,200 to their original approved task order and a timeline extension of 
6-8 weeks as a result of the agreed upon scope changes. The changes to the scope will net long term 
savings to the Commission over the life of the SCADA system due to the elimination of the $2,000 
monthly cost for a separate fiber internet connection which over an anticipated 7 year life of the system 
equates to a cost savings of over $150,000 in internet connection fees alone, amongst other reoccurring 
costs for data storage and back up. 
 
11. Water and Wastewater Standards and Specifications Update 
L.I. # 24431-52121 
Approved Task Order: $36,800.00 
Current Project Status: Two working sessions with Waterford and New London staff were held on 
12/9/25 and 1/7/26 to review the W-P draft standards and specifications provided. One more session is 
scheduled for next Wednesday Jan 14th to finalize our reviews; mark ups from these sessions will be 
provided to W-P to incorporate in a revised draft. 
Project Background: The current Water and Wastewater Standard and Specifications the Utility 
Commission uses are significantly outdated and require updating. This project is being cost-shared with 
the City of New London.  
Other Utility Commission Updates 
• 
Reliant Land and Water was awarded the contract for Engineering Services to Identify the Capital 
requirements surrounding the potential renewal of the Waterford/New London Interlocal Water 
Agreement.  
• 
Flow metering – EST came out and visited all our metering locations with Utility Commission staff. A 
proposal for quarterly site visits for sensor cleaning and calibrations to be conducted by EST, along with 
minor equipment upgrades required to migrate all our meters to an online platform enabling direct 
access and report generation will be provided to the Commission at the Jan 13th meeting after some 
revisions are made. 
 
Respectfully Submitted, 
Jill N. Stevens 
Director of Utilities