WATERFORD UTILITY COMMISSION
DATE:
January 14, 2025
PLACE:
1000 Hartford Turnpike
PRESIDING:
Chairman Ken Kirkman
MEMBERS PRESENT:
Tom Dembek, Ray Valentini, Rodney Pinkham and Jerry Porter
ALSO PRESENT:
Attorney Nicholas Kepple, Town Counsel
Staff: Jill Stevens, Director of Utilities
Shawn Matthews, Assistant Director of Utilities
Chairman Kirkman called the meeting to order at 6:00 pm
CITIZEN SESSION-
None
SECRETARY’S REPORT
MOTION
Made by Mr. Valentini to approve the Minutes of December 10th, 2024, Mr.
Dembek seconded.
VOTE
The motion passed unanimously.
BILLING ADJUSTMENTS
The Commission reviewed the December adjustments. The adjustment report will be kept in the
office for review.
EXPENDITURES
MOTION
Made by Mr. Pinkham to approve the December 2024 bill list, Mr. Dembek
seconded.
VOTE
The motion passed unanimously.
OLD BUSINESS
•
Director’s Report
Ms. Stevens reviewed her report that provides updated information on all Utility
Commission Capital and Operational projects that are currently funded and the status of
each project. A copy of the Director’s Report will be attached to the minutes when
posted.
Waterford Utility Commission
January 14, 2025
2 | P a g e
•
Collection’s Report
Attorney Kepple reported that collection continues to go well. He did explain that the
number of files with large amounts of money to be collected are starting to go down
because they have been collected. That is why the summary of Fiscal Year totals are
starting to decline. This is a great step in the right direction.
•
Financial Report
The financials for November were reviewed.
•
Ad-Hoc Water Committee
Mr. Valentini reported that they have not met but will be setting another date shortly.
NEW BUSINESS
None
WATER
City of New London/Veolia Report.
The report was reviewed by the Commission.
CORRESPONDENCE
E-mail from resident regarding his late Sewer Deduct Meter reading. This is tabled until next month
meeting.
PLANS REVIEW –
None
PERSONNEL
•
Sewer Tech I
The position was re-posted at the beginning of January
•
Compliance Enforcement Tech Posting
Edward Machinski will be starting on January 21st.
OTHER
ADJOURNMENT
With no further business before the Commission, the meeting adjourned at 7:01 p.m.
MOTION
Made by Mr. Pinkham to adjourn, Mr. Valentini seconded.
VOTE
The motion passed unanimously.
Respectfully submitted,
Amy Windle
Recording Secretary
P a g e | 1
Waterford Utility Commission
Director’s Report
January 9, 2025
This report summarizes the Commission’s ongoing projects and operational activities as of 1/9/25
Current Capital and Capital Non-Recurring Funded Projects
1. Inflow and Infiltration Mitigation and Control
FY 19 Capital & Non-Recurring Expenditure Fund L.I. #20531-57685
Original Appropriation: $388,303.00 Available Balance: $237,214.39
This is an ongoing project. To identify sources of Inflow and Infiltration within the Richards Grove Sewer
Basin. A draft report was emailed on October 30, 2024 for review and comment, staff reviewed and
issued comments back to Wright Pierce to address within the report. As of 1/9/2025 Wright Pierce
continues to work on responses to our comments, a meeting to discuss flow meter relocation is
tentatively scheduled for Thursday this week.
Field data and video review and QA/QC will be completed by Friday, September 13, 2024 with a target
date of September 27th for the draft report. No major manhole defects were noted. All field testing is
completed (manhole inspections, smoke testing). Wright Pierce is reviewing the field-testing results and
working a Technical Memorandum with the results. Manhole inspections were conducted on July 15
followed by Smoke testing of the sewer mains on July 16th. The Richards Grove Road Wastewater Basin
I&I evaluation being conducted by Wright-Pierce Engineers for the amount of $27,500.00 This project
consist of conducting inflow and infiltration I&I evaluations and Sewer System Evaluation Study (SSES) .
This drainage area has been identified as one of the larger contributors of I&I to our Collection System.
This area possesses approximately 5 miles of 8-inch diameter gravity sewer piping and
serves primarily residential users. The current flows received and conveyed by the Richards Grove
Pump Station are greater than the current capacity of the pump station, triggering the potential need
for a capacity upgrade if the I & I sources cannot be identified and mitigated. The I&I mitigation and
control program is an ongoing project. Our staff routinely conducts pipeline and manhole assessments
with the use of our CCTV and Jet Rodding apparatus. Deficiencies are located, graded and catalogued
based upon severity. Corrective repairs are typically conducted during springtime utilizing robotic
trenchless technology.
P a g e | 2
2. Old Norwich Road Wastewater Pump Station Rehabilitation
There are two CNR designations totaling $1,299,369 in L.I. # 20531-57816.
Available CNR Balance: $160,595.91
In addition, available ARPA funds in the amount of $1,020,041.
The new roof was installed in June. Stored materials have been relocated from the Holzner warehouse to
a storage container box located at the pump station.
Contractor submittals ongoing (approximately 85% complete with submittals). Contractor completion
date remains November of 2025 currently.
The updated construction schedule is as follows:
•
Install new doors & trim: The doors and trim work is nearly complete, a few minor punch list items
remain, and the mismatched ridge cap has been replaced.
•
Power wash building & fencing at fuel tank – will be completed when doors are installed
•
Gas line install to building – Eversource installed the line on Thursday 9/19.
•
Gas line run from regulator/ meter to building entrance – Holzner/ mechanical contractor ran
underground gas line from regulator to north side.
•
Switchgear is showing delivery late spring – once received, bulk of work will commence
•
Bypass install / contractor mobilization – early May
•
Electrical installation – commence once bypass system in place
•
Mechanical installation - commence once bypass system in place
•
Final site work – commence after bypass system removal
Competitive bid results for this project were received on August 10, 2023. The lowest bid received was
from Holzner Construction in the amount of $2,113,850.00 The Notice to Proceed for Holzner was
executed on January 16, 2024. A Contract Administration proposal from Wright- Pierce was executed
1/19/2024 in the amount of $55,800.00 an anticipated completion date is expected about November
2025.
3. Control Panel Retrofit
FY22 Capital Improvement Fund L.I. # 33122-55894
Original Appropriation: $30,000.00 Available Balance: $0 – line closed
All ordered parts have arrived, we anticipate beginning this project in the next 3-4 weeks once
Ridgewood Ave is complete. This project entails replacing the existing pump control panels, which are
obsolete and unsupported with current control technology. This work will ensue upon completion of
upgrades currently being conducted at 10 of the lift stations, which are identified within this report and
are being funded with ARPA funds.
4. Pump Station Exterior Improvements
FY22&23 Capital Improvement Fund L.I. # 33123-55895
Original Appropriations: $ 100,000.00 (50K ea. L.I.) Available Balance: $15,412.84
The East Neck Station driveway was replaced and the roof at Evergreen Avenue was replaced.
To date under these two L.I.#s, roof replacements have occurred at Shore Road, Dock Road, Bolles Ct,
Waterford Village, Sea Side, Niantic River Rd, Mago Pt and Evergreen Ave stations. The exterior siding
was replaced at the Waterford Village and Bolles Ct stations. Siding repairs were conducted at Stoney
Brook Station. A new asphalt driveway was installed at the East Neck pump station. This program will
reconvene in the spring of 2025 with a driveway replacement at Cross Road Station.
P a g e | 3
5. Gorman-Rupp Pump Station Controls
This is an ARPA allocation project in the amount of $163,750.00. L.I. # 23531-55013
To date Shore Road, Dock Road, Richards Grove Road, Old Barry Road, Quaker Hill Center, Oil Mill,
Oswegatchie Rd and Niantic River Road stations are complete; Ridgewood Ave station, is the last station
for this project and is at approximately 50% complete, we anticipate the remaining work will take 2-3
weeks. Utility Commission staff is performing the installation of equipment, conduits and wiring. A scope
of services change order was executed that directs the contractor to supply 18 cellular amplifiers and
associated equipment in lieu of providing broadband to 5 stations. Utility Commission staff will be
installing the amplifiers during the process of the controls upgrades. This project is ongoing.
6. Contract #1 Sewer Easement Access Project.
Capital Improvement Fund L.I. # 33123-55019
Original Appropriation: $250,000.00
Available Balance $174,800.00
A quick kick off call to begin the final design package (drawing and specs) to be used for contractor bid
solicitation and construction for Phase One of the restoration project occurred on December 17, however
more discussions are needed; a follow up meeting is tentatively set for next week. Phase one will
encompass the southern section of the interceptor beginning at the intersection of Great Neck Road and
Rope Ferry Road to the end of the Interceptor at Evergreen Pump Station. Phase two which encompasses
the northern section of the interceptor from Boston Post Road to Great Neck Road requires the
acquisition of additional easements to gain access to the interceptor during restoration and for the Utility
Commission staff in the future. Splitting the project into two Phases allows restoration work to begin
while easements are procured, so that once Phase one is complete easements will be in place and Phase
two can begin shortly thereafter.
Contract One Restoration Preliminary Design: W-P and WUC to have Teams meeting (tentative for
Tuesday July 16) to discuss scope for the final design and construction. Also discuss the approach for 2
new easements that may be required for interceptor access. Based on the meeting, W-P will provide a
fee proposal for the final design package (drawing and specs) to be used for contractor bid solicitation
and construction.
The request for a Special Appropriation of funds in the amount of $500,000 was approved by the Board
of Selectmen on 1/10/23. On 1/11/23 the Board of Finance acted to reduce the original request
appropriation to $250,000. On 2/6/23 the RTM approved the $250,000.00 Special appropriation. On
August 8, 2023 the Utility Commission accepted Wright–Pierce Engineers (W/P) task order proposal in
the amount of $75,200.00. Survey of the C-1 easement started October 2, 2023 and is now complete.
Wright-Pierce (W/P) submitted the Preliminary drawings on February 6, 2024. A plan review session was
conducted on February 14, 2024 at which time we identified various access alternatives.
7. Plastic Water Service Line Replacement Program
CNR Appropriation L.I. # 20531-57881
Original Appropriations: $550,000.00+$181,300.00 = $731,300.00
Available Balance: $426,391.18
An additional 100K was designated FY24, a request to move from an appropriation to a designation will
take place when the currently appropriated funds are expended.
P a g e | 4
The Maintenance crew has completed work on Quarry Road, Goshen Road, Leary Drive and Country Club
Drive, a total of 65 services were investigated, of which 41 were identified as plastic service lines and
replaced, this amounted to 972 LF of service line replacement on these streets. The replacement of
services previously scheduled for Old Norwich Rd is now pushed off until the spring of next year; this
work will likely be put out to bid to allow the Maintenance staff to focus on smaller roads and also to
keep up with their other system maintenance tasks.
Work commenced on the Plastic Water Service Replacement Project on May 22, 2023. In Fiscal Year 2024
the City of New London’s contract service provider, Veolia replaced 21 plastic services on Shore Road;
Waterford Utility Commission Maintenance Staff investigated a total of 425 services of which 105 were
identified as plastic services and replaced on Shore Road, Niantic River Road, Tiffany Ave, East Brook
Drive, Savi Ave, Cherry Street, Willow Street, Cedar Street, Mackenzie Road, Lark Street, Thrush Street,
Robin Street, Quail Street, Kingfisher Way, Kestrel Lane, Woodlawn Ave and Woodlawn Court; a total of
2,584 LF of service lines were replaced. A request for an additional $181,300.00 to replace plastic water
services on Old Norwich Rd was approved by the Board of Selectman, Board of Finance and subsequently
by the RTM on August 7, 2023.
8. Wiemes & Marilyn Road Ejector Pump Replacement
CNR Designation L.I. # 20531-57890
$19,800.00
On January 7th, the Board of Selectmen approved our request to appropriate the designated funds, and
forward the request to the Board of Finance meeting scheduled for January 15th. Pending Board of
Finance approval, the request should be on the February 2nd RTM agenda for final approval and funds will
be available 15 days thereafter, as which time the task order will be signed and the Engineering Study can
begin.
Wiemes Ct and Marilyn Rd pump stations were designed in 1981. These stations are known as Pneumatic
Ejectors. The station itself is a steel cylinder 9' in diameter buried about 18 feet below ground and
accessed via a manway. The station houses the pots, compressors and control panel. The stations have
exceeded their design life and do not operate efficiently. An engineering study is warranted to fully
evaluate the stations structural integrity and plan for the station's replacement. In addition,
considerations for permanent stand by power should be evaluated, as portable generators have to be
mobilized in the event of need. Wright-Pierce provided a fee proposal for $19,800 to complete the
needed engineering study, a formalized task order has been requested, with the understanding the
funding must be appropriated prior to execution of the task order.
Sewer Development & Maintenance Fund Projects
9. SCADA System Upgrade Design/Build
L.I. # 24431-57766
$147,600.00
The current SCADA (Supervisory Control and Data Acquisition) system has experienced multiple failures
over the past several months, which has necessitated calling in the entire crew to canvas the pumps
stations on at least one occasion while the system was brought back online; additionally two different
software programs used to operate the system are no longer supported and the hardware has exceeded
its useful life. The Commission has entered into a design-build contract with Wright Pierce, our on-call
engineering firm, to replace the failing system. The new system platform will be Ignition, a software
system found and piloted by one of our current Maintenance Operators and presented to the
P a g e | 5
Commission over the past few years. Additionally the communication between stations to the
maintenance shop/Municipal Complex will be accomplished over a closed zero-tunnel cellular network
with radio redundancy. The Commission approved the proposal from Wright-Pierce for this project in
August of 2024, the cellular network work is outside of this proposal and is being handled by Utility
Commission staff. As a result of discussions and investigations made over the last few months, an
amendment to the scope of the project will be made. This amendment was discussed at the December
meeting with a representative from Wright-Pierce and involved avoiding duplicative efforts in terms of IT
infrastructure/resources that the Town could provide the Commission, including options for fiber
connectivity, data storage, and virtualized hosts.
To date the following progress has been made on this project:
1) Project kickoff meeting held on site October 3rd. Wright-Pierce reviewed the current network
architecture and programs/ hardware.
2) Preliminary network architecture drawings in progress, coordination meeting with Waterford IT on
Dec 6h.
3) Revised preliminary network drawings based on initial/follow up discussions.
4) Verizon design meeting to review cellular network needs
5) IT meeting to discuss virtual historian and data storage.
6) Commission meeting to review modified scope per above
7) A follow up IT meeting to solidify scope changes for forthcoming amendment.
Utility Commission Operational Projects
•
All wastewater collection system components and equipment are operational with exception of:
1. Pump number 1, the Ed Machinski, at Evergreen is offline a replacement pump installation is
underway at Evergreen. Pump startup was attempted on January 8th, while start up went smoothly
and the pump performs well, there was a concern around the level of vibration, which were barely
within the Hydraulic Institute’s specified limits. The contractor, pump manufacturer and our staff
will be on site on Feb 4th to check for pipe strain which could be contributing to the elevated
vibration levels.
•
O’Neill Theater tie-in for The Barn and Production Cottage, the Utility Commission and Public Works
have partnered on this project to connect the back half of the theater building (The Barn) and the
Production Cottage to our system. This work was completed by our on-call contractors and WUC/DPW
staff. The contractor’s scope is complete; some site work / beautification will be completed by DPW staff
in the spring, and an assessment surrounding the need for a vent for the station and its location by WUC
staff.
•
The Asset Management software project, Beehive, is underway and improvements to our GIS program
continue. Initial training for Beehive is scheduled for January 21st.
•
Municipal Waterworks Meetings: a meeting was held via Zoom on January 8th.
•
Municipal Wastewater Flow Metering verification was performed by an independent vendor, the Utility
Commission continues to work with New London to come to terms with meter types and locations to
move forward and resolve the flow data discrepancies.
Respectfully Submitted,
Jill N. Stevens
Director of Utilities